14959 W MARLIN PL 91405

Certificate Information: 14959 W MARLIN PL 91405

Application / Permit
22010-20000-05886
Plan Check / Job No.
B22VN17771
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New Detached one-story Accesory Dwelling Unit PER LAMC 12.22 A.33(c) AND (d) at rear of the lot
Permit Issued
Issued on 2/8/2023
Issuing Office
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2022 APPLICANT
Assigned to Plan Check Engineer 12/9/2022 EDWIN ESPIN
Corrections Issued 12/12/2022 EDWIN ESPIN
Plan Check Approved 2/6/2023 EDWIN ESPIN
No Progress 2/6/2023 EDWIN ESPIN
Plan Check Approved 2/6/2023 EDWIN ESPIN
Issued 2/8/2023 APPLICANT
CofO in Progress 9/5/2023 RYAN SALAZAR
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/14/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 12/14/2022 RYAN KIM
Sewer availability Cleared 12/14/2022 RYAN KIM
Low Impact Development Cleared 12/20/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/21/2022 RYAN KIM
Hydrant and Access approval Cleared 1/30/2023 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/13/2023 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 3/17/2023 Conditional Approval JOHN COLEMAN
BUILDING-Rough-Frame 4/18/2023 Corrections Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Partial Approval RYAN SALAZAR
Green Building Rough 4/18/2023 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 4/18/2023 Approved RYAN SALAZAR
Deputy Wood Construction 4/21/2023 Conditional Approval JUAN VALENZUELA
Wood Frame 4/25/2023 Approved RYAN SALAZAR
HVAC-Rough 5/9/2023 Approved RYAN SALAZAR
PLUMBING-Rough 5/9/2023 Approved RYAN SALAZAR
Sewer 5/9/2023 Approved RYAN SALAZAR
Insulation 5/19/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/24/2023 Approved RYAN SALAZAR
Drywall Nailing 5/24/2023 Approved RYAN SALAZAR
Green Building Rough 5/24/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/5/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 7/24/2023 Corrections Issued JENNIFER RABUCHIN
Final 7/24/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/24/2023 Approved JENNIFER RABUCHIN
Green Building Final 7/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 7/24/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/24/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 7/24/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 7/24/2023 Approved JENNIFER RABUCHIN
Final 8/28/2023 OK to Issue CofO RYAN SALAZAR
Reinforced Concrete Frame 8/28/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 8/28/2023 Approved RYAN SALAZAR