16055 W INDEX ST 91344

Certificate Information: 16055 W INDEX ST 91344

Application / Permit
22010-20000-05804
Plan Check / Job No.
B22VN17569
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 4/27/2023
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 CARLOS MONTES
Corrections Issued 12/15/2022 CARLOS MONTES
Quality Review Completed 12/20/2022 GARO TELMI
Applicant returned to address corrections 2/15/2023 CARLOS MONTES
Applicant returned to address corrections 3/8/2023 CARLOS MONTES
Plan Check Approved 3/17/2023 CARLOS MONTES
Issued 4/27/2023 APPLICANT
CofO in Progress 12/3/2024 JAVIER RAMOS JR
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/20/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/27/2022 COLIN LOREDO
Low Impact Development Cleared 1/25/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/25/2023 COLIN LOREDO
Sewer availability Cleared 1/26/2023 COLIN LOREDO
Construction near power lines Cleared 1/30/2023 WALTER RAMIREZ
GPI Written Notices Cleared 3/15/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 3/15/2023 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 11/27/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/8/2023 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 12/8/2023 Conditional Approval KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/12/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 12/20/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 1/29/2024 Approved JAVIER RAMOS JR
Sewer 1/29/2024 Approved JAVIER RAMOS JR
Underground Mechanical 1/29/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/28/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Partial Approval CRAIG DAVIS
Green Building Rough 2/28/2024 Not Ready for Inspection CRAIG DAVIS
Verify Sprinkler Sign Off 2/28/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 3/26/2024 Approved JAVIER RAMOS JR
HVAC-Rough 3/26/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 3/26/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/27/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval JAVIER RAMOS JR
Green Building Rough 3/27/2024 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/4/2024 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Approved JAVIER RAMOS JR
Green Building Rough 4/4/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/4/2024 Approved JAVIER RAMOS JR
Insulation 4/18/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/18/2024 Partial Approval JAVIER RAMOS JR
Insulation 4/29/2024 Approved JAVIER RAMOS JR
Shower Pan 4/29/2024 Approved JAVIER RAMOS JR
Drywall Nailing 5/22/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 7/26/2024 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 10/9/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/9/2024 Partial Inspection JAVIER RAMOS JR
Final 10/9/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/9/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 10/9/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 10/9/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 10/9/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 10/31/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/31/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 10/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 11/8/2024 Approved JAVIER RAMOS JR
Final 11/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 11/8/2024 Approved JAVIER RAMOS JR
HVAC-Final 11/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 11/8/2024 Approved JAVIER RAMOS JR
Smoke Detectors 11/8/2024 Approved JAVIER RAMOS JR
Final 12/3/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 12/3/2024 Approved JAVIER RAMOS JR