4445-4447 N GENTRY AVE 91607

Certificate Information: 4445-4447 N GENTRY AVE 91607

Application / Permit
22010-20000-05794
Plan Check / Job No.
B22VN17548
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 38' x 73'-9" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c)(1)(iii)] AND ATT. 2-CAR GARAGE; NFPA-13D THRU-OUT
Permit Issued
Issued on 4/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 SEAN SHAHMIRI
Corrections Issued 12/27/2022 SEAN SHAHMIRI
Quality Review Completed 12/28/2022 OMID HEDAYAT
Building Plans Picked Up 1/4/2023 APPLICANT
Plan Check Approved 3/23/2023 SEAN SHAHMIRI
No Progress 3/28/2023 SEAN SHAHMIRI
Plan Check Approved 4/5/2023 SEAN SHAHMIRI
Issued 4/5/2023 APPLICANT
CofO in Progress 11/1/2024 CHRISTOPHER ROJAS
No Progress 11/2/2024 JUAN VALENZUELA
CofO in Progress 11/20/2024 CHRISTOPHER ROJAS
CofO in Progress 12/5/2024 CHRISTOPHER ROJAS
Permit Finaled 12/18/2024 RUBEN SALAS
CofO Issued 12/18/2024 RUBEN SALAS
Permit Finaled 12/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/3/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/4/2023 CARLOS AGUILERA
Sewer availability Cleared 1/4/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/26/2023 MATTHEW CRAIG
Trees in Parkway Cleared 2/4/2023 ADALBERTO VERA
Low Impact Development Cleared 3/10/2023 MARTIN FRAGOSO
Permit Cleared 3/13/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/13/2023 CARLOS AGUILERA
ZI Cleared 3/14/2023 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/12/2023 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/17/2023 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 4/17/2023 Corrections Issued JACK KARGODORIAN
Deputy Reinf. Concrete 4/20/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/25/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 5/8/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval JACK KARGODORIAN
Gas Test 6/7/2023 Not Ready for Inspection JACK KARGODORIAN
Pre-Gunite 6/7/2023 Partial Approval JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Not Ready JACK KARGODORIAN
Special/Order Compliance 6/22/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 7/11/2023 Corrections Issued JACK KARGODORIAN
HVAC-Rough 7/11/2023 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 7/11/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 7/14/2023 Approved JACK KARGODORIAN
HVAC-Rough 7/14/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 7/14/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 7/17/2023 Corrections Issued JACK KARGODORIAN
Green Building Rough 7/17/2023 Approved JACK KARGODORIAN
MERV13>=Rough 7/17/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 7/17/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/31/2023 Partial Approval DAVID MATSON
Interior/Exterior Lathing 8/4/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 8/8/2023 Approved DAVID MATSON
Interior/Exterior Lathing 8/8/2023 Corrections Issued DAVID MATSON
Shower Pan 8/10/2023 Approved JACK KARGODORIAN
Drywall Nailing 8/14/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Enclosure/Fence 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 9/9/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 9/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 9/9/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 9/12/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 9/17/2024 Approved SALVADOR MARTINEZ
HVAC-Final 9/20/2024 Approved CHRISTOPHER ROJAS
Final 10/9/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/9/2024 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Final 10/9/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 10/9/2024 Partial Inspection CHRISTOPHER ROJAS
Final 10/17/2024 Conditional Approval CHRISTOPHER ROJAS
Green Building Final 10/17/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 10/17/2024 Approved CHRISTOPHER ROJAS
Final 11/20/2024 Corrections Issued CHRISTOPHER ROJAS
Final 12/5/2024 OK to Issue CofO CHRISTOPHER ROJAS