10706 W ART ST 91040
Certificate Information: 10706 W ART ST 91040
- Application / Permit
- 22010-20000-05781
- Plan Check / Job No.
- B22VN17521
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 52' X 62'-2" ONE STORY SINGLE FAMILY DWELLING PER SB9 ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- Issued on 11/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/3/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/5/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/27/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/13/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 11/8/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 7/18/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 8/22/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 9/3/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/10/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/24/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/1/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/20/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/17/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 1/17/2023 | NATHAN ROMINE |
| Grading Pre-Inspection | Cleared | 1/19/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 2/17/2023 | ROMAN GUTIERREZ |
| Address approval | Cleared | 3/10/2023 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 6/28/2023 | LAVEON RIDER |
| Low Impact Development | Cleared | 9/21/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/12/2023 | COLIN LOREDO |
| GPI Written Notices | Cleared | 10/13/2023 | SEWADA ZADOORAN MILAGARDI |
| Miscellaneous | Cleared | 7/23/2024 | NELSON RODRIGUEZ |
| Senate Bill 9 | Cleared | 7/23/2024 | NELSON RODRIGUEZ |
| Specific Plan | Cleared | 7/23/2024 | NELSON RODRIGUEZ |
| Specific Plan | Cleared | 10/2/2024 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/26/2024 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 4/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 5/5/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 7/21/2025 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 10/20/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/20/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 10/20/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 10/23/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/26/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/9/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/9/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/15/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/15/2026 | Corrections Issued | DAVID ANDERSON |