11518 N MAGEE AVE 91331

Certificate Information: 11518 N MAGEE AVE 91331

Application / Permit
22010-20000-05768
Plan Check / Job No.
B22VN17488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 30' X 40' DETACHED ACCESSORY DWELLING UNIT WITH A 5' X 6' PORCH PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENG.
Permit Issued
Issued on 9/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/30/2022 MADISON ODELL
Corrections Issued 12/1/2022 MADISON ODELL
Building Plans Picked Up 12/1/2022 APPLICANT
Applicant returned to address corrections 9/13/2023 LUISANGEL VALENZUELA
Issued 9/14/2023 APPLICANT
CofO in Progress 9/9/2024 MICHEL ABAJAN
Permit Finaled 9/17/2024 DANIEL ORRANTE
CofO Issued 9/17/2024 DANIEL ORRANTE
Permit Finaled 9/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 5/5/2023 TINA MIRANDA
Construction within easement Cleared 5/5/2023 TINA MIRANDA
Address approval Cleared 7/24/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/24/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/24/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 9/12/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/13/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Valenzuela Pancho Construction; Lic. No.: 1067736-B 544 ORANGE GROVE AVE      SAN FERNANDO, CA 91340
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 11/6/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/19/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/19/2023 Conditional Approval MICHEL ABAJAN
Green Building Rough 12/19/2023 Approved MICHEL ABAJAN
HVAC-Rough 12/19/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/19/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 12/19/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/19/2023 Approved MICHEL ABAJAN
Insulation 12/22/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/22/2023 Approved MICHEL ABAJAN
Drywall Nailing 12/27/2023 Approved MICHEL ABAJAN
Underground Mechanical 4/3/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/10/2024 Approved MICHEL ABAJAN
Final 5/10/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 5/10/2024 Approved MICHEL ABAJAN
HVAC-Final 5/10/2024 Approved MICHEL ABAJAN
MERV13>=Final 5/10/2024 Approved MICHEL ABAJAN
PLUMBING-Final 5/10/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 5/10/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 5/10/2024 Approved MICHEL ABAJAN
Final 5/16/2024 Conditional Approval MICHEL ABAJAN
Service/Power Release 5/16/2024 Approved MICHEL ABAJAN
Final 9/9/2024 OK to Issue CofO MICHEL ABAJAN