13833 W BESSEMER ST 91401
Certificate Information: 13833 W BESSEMER ST 91401
- Application / Permit
- 22010-20000-05753
- Plan Check / Job No.
- B22VN17444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 44'5" X 27'-0" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/24/2024
- Issuing Office
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 12/25/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 12/29/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/6/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/20/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 6/29/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 1/10/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/1/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 5/24/2024 | APPLICANT |
| CofO in Progress | 6/25/2025 | RYAN SALAZAR |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
| CofO Issued | 7/1/2025 | RUBEN SALAS |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2023 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/11/2023 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 10/21/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/21/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/28/2024 | MARTIN FRAGOSO |
| Construction near power lines | Cleared | 1/30/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/30/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: NA66727 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/24/2024 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 10/29/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 11/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Reinforced Concrete Frame | 11/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Corrections Issued | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | No Access for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/10/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/24/2025 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/31/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/20/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/20/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/20/2025 | Approved | RYAN SALAZAR |
| Insulation | 2/24/2025 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/4/2025 | Conditional Approval | RYAN SALAZAR |
| Shower Pan | 3/26/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Sewer | 4/11/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/16/2025 | Approved | RYAN SALAZAR |
| Final | 5/16/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/16/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Not Ready | RYAN SALAZAR |
| Service/Power Release | 5/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 5/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 6/17/2025 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 6/17/2025 | Approved | RYAN SALAZAR |
| Final | 6/24/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 6/24/2025 | Approved | RYAN SALAZAR |