991-991 1/2 E 51ST ST 90011
Certificate Information: 991-991 1/2 E 51ST ST 90011
- Application / Permit
- 22010-20000-05751
- Plan Check / Job No.
- B22VN17440
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY DETACHED (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) **The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy**
- Permit Issued
- Issued on 5/31/2023
- Issuing Office
- Current Status
- Issued on 5/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/20/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/20/2022 | STEVEN KIM |
| Applicant returned to address corrections | 2/24/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/28/2023 | NILOOFAR MEHRAIN |
| Issued | 5/31/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2022 | AMAAN MALIK |
| ZI | Cleared | 12/30/2022 | MAXFIELD VERMY |
| Roof/Waste drainage to street | Cleared | 1/10/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/13/2023 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 1/22/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Smoke Detectors | 7/20/2026 |
| Final | 7/20/2026 |
Inspection Request History
| Underground Mechanical | 8/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/19/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/9/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/3/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/3/2024 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/3/2024 | Approved | MICHAEL LEWIS |
| Insulation | 6/17/2024 | Approved | JOSH MEISTER |
| Wood Frame | 6/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/1/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/7/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/12/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 9/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/10/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/10/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/10/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/10/2026 | Approved | ALEJANDRO DE ARTOLA |