18051 W MAYERLING CT 91344

Certificate Information: 18051 W MAYERLING CT 91344

Application / Permit
22010-20000-05734
Plan Check / Job No.
B22VN17410
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW ADU WITH ATTACHED TRELLIS PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/12/2023
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 MAHNAZ NOURHASHEMI
Corrections Issued 12/8/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 12/9/2022 GARO TELMI
Plan Check Approved 4/14/2023 MAHNAZ NOURHASHEMI
Issued 5/12/2023 APPLICANT
CofO in Progress 1/15/2025 STEVEN BACK
No Progress 4/2/2025 HENRY KIM
CofO in Progress 4/2/2025 HENRY KIM
Permit Finaled 4/14/2025 JOHN JANSON
Permit Finaled 4/14/2025 JOHN JANSON
CofO Issued 4/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/19/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/14/2023 KURT CORRAL
Low Impact Development Cleared 2/14/2023 LUIS LUVANO
ZA Case Cleared 2/14/2023 MIGUEL GAMBOA
ZA Case Cleared 2/14/2023 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 2/21/2023 LEE GUILBEAUX
Sewer availability Cleared 2/21/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/22/2023 DAGOVERTO GUERRERO
GPI Written Notices Cleared 4/14/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 4/14/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2023 Approved SEAN HAUPT
Grounding or Bonding 5/16/2023 Approved SEAN HAUPT
PLUMBING-Rough 5/30/2023 Partial Approval STEVEN BACK
Wood Frame 5/30/2023 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 7/3/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Corrections Issued STEVEN BACK
Rough-Elec/Plmb/HVAC 7/3/2023 Approved STEVEN BACK
Verify Sprinkler Sign Off 7/3/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 7/10/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Approved STEVEN BACK
Interior/Exterior Lathing 7/10/2023 Partial Approval STEVEN BACK
Underground Mechanical 7/10/2023 Approved STEVEN BACK
Drywall Nailing 7/24/2023 Approved HENRY KIM
Insulation 7/24/2023 Approved HENRY KIM
Interior/Exterior Lathing 8/29/2023 Approved SEAN WIRCH
Shower Pan 8/29/2023 Approved SEAN WIRCH
Final 12/3/2024 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved STEVEN BACK
Service/Power Release 12/3/2024 Not Required STEVEN BACK
Smoke Detectors 12/3/2024 Approved STEVEN BACK
Final 1/15/2025 OK to Issue CofO STEVEN BACK