8604 N ROBERT AVE 91352

Certificate Information: 8604 N ROBERT AVE 91352

Application / Permit
22010-20000-05719
Plan Check / Job No.
B22VN16206
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Construct new 2-story detached ADU at rear of lot per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/14/2023
Issuing Office
Current Status
CofO Issued on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 SHANGQIN XIE
Corrections Issued 11/15/2022 ALFRED RAMIREZ
Applicant returned to address corrections 12/10/2022 SHANGQIN XIE
Plan Check Approved 3/22/2023 SHANGQIN XIE
Issued 4/14/2023 APPLICANT
CofO in Progress 12/29/2023 DAVID ANDERSON
Permit Finaled 1/31/2024 RUBEN SALAS
Permit Finaled 1/31/2024 RUBEN SALAS
CofO Issued 1/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/12/2022 COLIN LOREDO
Clean Up Green Up Cleared 12/13/2022 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 1/5/2023 COLIN LOREDO
Hydrant and Access approval Cleared 1/22/2023 KURT CORRAL
Construction near power lines Cleared 2/22/2023 RIDWAN HARDY
Low Impact Development Cleared 3/15/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/17/2023 CARLOS AGUILERA
Sewer availability Cleared 3/17/2023 CARLOS AGUILERA

Contact Information

Architect Dellos,, Wendy Guadalupe; Lic. No.: NA36239       ,
Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2023 Approved DAVID ANDERSON
Sewer 5/17/2023 Approved DAVID ANDERSON
Underground Mechanical 5/17/2023 Off-Hour Fees Due
Underground Mechanical 5/17/2023 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 6/21/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval DAVID ANDERSON
HVAC-Rough 6/21/2023 Approved DAVID ANDERSON
PLUMBING-Rough 6/21/2023 Approved DAVID ANDERSON
Wood Frame 6/21/2023 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 6/26/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Approved DAVID ANDERSON
Green Building Rough 6/26/2023 Approved DAVID ANDERSON
MERV13>=Rough 6/26/2023 Approved DAVID ANDERSON
Shower Pan 6/26/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 6/26/2023 Approved DAVID ANDERSON
Insulation 7/5/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/5/2023 Approved DAVID ANDERSON
Drywall Nailing 7/19/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/19/2023 Approved DAVID ANDERSON
Final 11/21/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 11/21/2023 Approved DAVID ANDERSON
Green Building Final 11/21/2023 Approved DAVID ANDERSON
MERV13>=Final 11/21/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 11/21/2023 Approved DAVID ANDERSON
Smoke Detectors 11/21/2023 Approved DAVID ANDERSON
Final 12/6/2023 Corrections Issued DAVID ANDERSON
Final 12/29/2023 OK to Issue CofO DAVID ANDERSON