13044 W HARTSOOK ST 91423

Certificate Information: 13044 W HARTSOOK ST 91423

Application / Permit
22010-20000-05717
Plan Check / Job No.
B22VN17340
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 41' X 13' ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 5/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/7/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/8/2022 OMID HEDAYAT
Building Plans Picked Up 12/13/2022 APPLICANT
Applicant returned to address corrections 2/23/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/7/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/17/2023 SEWADA ZADOORAN MILAGARDI
Issued 3/21/2023 APPLICANT
CofO in Progress 5/7/2024 JOSE AVILA
Permit Finaled 5/13/2024 RUBEN SALAS
CofO Issued 5/13/2024 RUBEN SALAS
Permit Finaled 5/13/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/9/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/9/2023 CARLOS AGUILERA
Sewer availability Cleared 1/9/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/6/2023 CARLOS AGUILERA
Construction near power lines Cleared 3/16/2023 WALTER RAMIREZ
Construction within easement Cleared 3/16/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/2/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/2/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 5/9/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/12/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 5/12/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Approved DAVID ANDERSON
Deputy Wood Construction 6/28/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Approved KIRK SANDERS
HVAC-Rough 6/28/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 6/28/2023 Approved KIRK SANDERS
HVAC-Rough 7/12/2023 Partial Approval KIRK SANDERS
Shower Pan 7/12/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/14/2023 Partial Approval KIRK SANDERS
Insulation 7/14/2023 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 7/14/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 7/25/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 7/25/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/4/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 8/7/2023 Partial Approval KIRK SANDERS
Green Building Rough 8/7/2023 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 8/7/2023 Approved KIRK SANDERS
Insulation 8/11/2023 Approved WILLIAM WREN
Drywall Nailing 8/17/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 8/17/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/17/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/9/2023 Partial Inspection MICHEL ABAJAN
Wood Frame 9/9/2023 Approved MICHEL ABAJAN
Wood Frame 9/9/2023 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 12/18/2023 Approved KIRK SANDERS
Drywall Nailing 12/18/2023 Approved KIRK SANDERS
ELECTRICAL-Final 12/18/2023 Corrections Issued KIRK SANDERS
Final 12/18/2023 Corrections Issued KIRK SANDERS
Green Building Final 12/18/2023 Approved KIRK SANDERS
HVAC-Final 12/18/2023 Approved KIRK SANDERS
PLUMBING-Final 12/18/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 12/18/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 12/18/2023 Approved KIRK SANDERS
ELECTRICAL-Final 3/5/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 3/5/2024 Approved JOSE AVILA
Final 3/6/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 4/5/2024 Corrections Issued JOSE AVILA
Final 4/5/2024 Corrections Issued JOSE AVILA
Service/Power Release 4/5/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 4/12/2024 Approved JOSE AVILA
Final 4/12/2024 Corrections Issued JOSE AVILA
Final 5/6/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 5/6/2024 Approved JOSE AVILA