22100 W ERWIN ST 91367
Certificate Information: 22100 W ERWIN ST 91367
- Application / Permit
- 22010-20000-05706
- Plan Check / Job No.
- B22VN17310
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (7) Carport
- Work Description
- NEW DETACHED CARPORT SUPPORTING PV SYSTEM. ARRAY NUMBER A1
- Permit Issued
- Issued on 11/17/2024
- Issuing Office
- Current Status
- Issued on 11/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | JOE VO |
| Corrections Issued | 12/3/2022 | JOE VO |
| Quality Review Completed | 12/6/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/7/2024 | JOE VO |
| Applicant returned to address corrections | 9/23/2024 | JOE VO |
| Applicant returned to address corrections | 10/8/2024 | JOE VO |
| Applicant returned to address corrections | 11/12/2024 | JOE VO |
| Plan Check Approved | 11/15/2024 | JOE VO |
| Issued | 11/17/2024 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/8/2022 | JOE VO |
| Hydrant and Access approval | Cleared | 5/23/2024 | KURT CORRAL |
| ZA Case | Cleared | 6/21/2024 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/25/2024 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 7/16/2024 | SARAH YOUSSEF |
| Fire Marshal Fire Life Safety | Cleared | 8/16/2024 | FIRE DEPARTMENT |
Contact Information
| Architect | Packard,, J Benjamin; Lic. No.: NA34479 | , |
| Contractor | Kahn M Solar Inc; Lic. No.: 982277-B | , |
| Contractor | Kahn Solar Construction; Lic. No.: 982277-B | , |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/7/2025 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Partial Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 4/10/2025 | Partial Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/25/2025 | Partial Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 4/25/2025 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/14/2025 | Conditional Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 8/6/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 8/7/2025 | Conditional Approval | JEFFREY DURAN |