8024 N YOLANDA AVE 91335

Certificate Information: 8024 N YOLANDA AVE 91335

Application / Permit
22010-20000-05688
Plan Check / Job No.
B22VN17277
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 41'-0" x 31'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) PER ENGINEERING
Permit Issued
Issued on 3/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 SERGIO MUNIZ
Corrections Issued 11/24/2022 SERGIO MUNIZ
Building Plans Picked Up 11/30/2022 APPLICANT
Plan Check Approved 2/3/2023 ALFRED RAMIREZ
Issued 3/17/2023 APPLICANT
CofO in Progress 9/5/2024 JEFFREY BULL
Permit Finaled 11/5/2024 JOHN JANSON
CofO Issued 11/5/2024 JOHN JANSON
Permit Finaled 11/5/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/30/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 11/30/2022 FERNANDO GIL
Sewer availability Cleared 12/1/2022 FERNANDO GIL
Low Impact Development Cleared 2/3/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/3/2023 CHRIS CHAHBAZ

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Valencia,, Byron Steve; Lic. No.: C87372 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/24/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 4/24/2023 Approved JEFFREY BULL
Underground Mechanical 4/24/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 4/25/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 7/13/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 7/13/2023 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 7/13/2023 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 7/13/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 7/18/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 7/18/2023 Partial Approval JEFFREY BULL
Rough-Elec/Plmb/HVAC 7/18/2023 Approved JEFFREY BULL
Special/Order Compliance 7/18/2023 Partial Inspection SEAN WIRCH
Deputy Drilled-In Anchors 7/19/2023 Approved JEFFREY BULL
Insulation 7/21/2023 Not Ready for Inspection JEFFREY BULL
Drywall Nailing 8/9/2023 Approved JEFFREY BULL
Sewer 8/9/2023 Approved JEFFREY BULL
Underground Mechanical 8/9/2023 Approved JEFFREY BULL
Final 5/29/2024 Corrections Issued JEFFREY BULL
Green Building Final 5/29/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready JEFFREY BULL
Service/Power Release 5/29/2024 Approved JEFFREY BULL
Smoke Detectors 5/29/2024 Approved JEFFREY BULL
Final 7/15/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 7/15/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Approved JEFFREY BULL
Final 9/5/2024 OK to Issue CofO JEFFREY BULL