20357 W WINDSOR LANE 91326
Certificate Information: 20357 W WINDSOR LANE 91326
- Application / Permit
- 22010-20000-05670
- Plan Check / Job No.
- B22VN17191
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 15'-6" x 22'-6" DETACHED PATIO COVER
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | SEAN SHAHMIRI |
| Corrections Issued | 11/25/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 12/1/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 12/2/2022 | APPLICANT |
| Plan Check Approved | 12/30/2022 | SEAN SHAHMIRI |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 9/18/2023 | STEVEN BACK |
| Permit Finaled | 9/21/2023 | JOHN JANSON |
| CofO Issued | 9/21/2023 | JOHN JANSON |
| Permit Finaled | 9/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 12/23/2022 | ROMAN GUTIERREZ |
| "T" removal | Cleared | 1/4/2023 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/4/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/4/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/4/2023 | ANACANY HURTADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 2/15/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/15/2023 | Approved | DAVID SCANTLIN |
| Deputy Steel/Welding | 2/23/2023 | Conditional Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 8/2/2023 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/16/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/16/2023 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 8/16/2023 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 8/18/2023 | Approved | STEVEN BACK |
| Final | 8/22/2023 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 8/22/2023 | Approved | STEVEN BACK |
| Final | 9/18/2023 | OK to Issue CofO | STEVEN BACK |