1128 W 46TH ST 90037

Certificate Information: 1128 W 46TH ST 90037

Application / Permit
22010-20000-05648
Plan Check / Job No.
B22VN17149
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'9" X 40'8" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK TO BE DONE PER WFPP.
Permit Issued
Issued on 10/26/2023
Issuing Office
Valley
Current Status
Issued on 10/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/18/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 SERGIO MUNIZ
Corrections Issued 11/25/2022 SERGIO MUNIZ
Building Plans Picked Up 12/2/2022 APPLICANT
Plan Check Approved 10/23/2023 MADISON ODELL
Issued 10/26/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/3/2023 AMAAN MALIK
Community Plan Implem. Overlay Cleared 2/10/2023 CINDY QI
Community Plan Implem. Overlay Cleared 6/12/2023 RIDWAN HARDY
Construction near power lines Cleared 6/12/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/14/2023 VICTOR MENDOZA
Specific Plan Cleared 9/11/2023 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 9/27/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 9/27/2023 JEANIE LAM
Sewer availability Cleared 9/27/2023 JEANIE LAM
Community Plan Implem. Overlay Cleared 10/19/2023 ADALBERTO VERA

Contact Information

Contractor E N B Construction Inc; Lic. No.: 990795-B 15115 PARTHENIA ST APT #232      NORTH HILLS, CA 91343

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/31/2023 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 11/13/2023 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved CRAIG DAVIS
Footing/Foundation/Slab 11/21/2023 Approved CRAIG DAVIS
Underground Mechanical 11/21/2023 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Approved CRAIG DAVIS
ELECTRICAL-Rough 12/15/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 12/21/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 12/21/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 12/21/2023 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 1/3/2024 Approved ANTHONY EGSON
Insulation 1/12/2024 Approved ENRIQUE MIRELES
Drywall Nailing 1/16/2024 Corrections Issued ALIZAH MAYAGOITIA
Sewer 1/26/2024 Approved RONNIE MINDANAO
Underground Mechanical 1/26/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 2/28/2024 Approved RONNIE MINDANAO
Shower Pan 2/28/2024 Approved RONNIE MINDANAO
Underground Mechanical 3/6/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 5/7/2024 Corrections Issued MICHAEL LEWIS
Gas Test 5/7/2024 Approved MICHAEL LEWIS
HVAC-Final 5/7/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 5/7/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 7/15/2024 Corrections Issued DAVID FEILER
HVAC-Final 7/15/2024 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 7/15/2024 Not Ready for Inspection DAVID FEILER
Service/Power Release 7/15/2024 Not Ready for Inspection DAVID FEILER
Smoke Detectors 7/15/2024 Approved DAVID FEILER