4440 N BEN AVE 91607
Certificate Information: 4440 N BEN AVE 91607
- Application / Permit
- 22010-20000-05639
- Plan Check / Job No.
- B22VN17113
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan NEW 2-STORY SINGLE FAMILY RESIDENCE WITH A NEW ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | JAD BASMA |
| Corrections Issued | 11/27/2022 | JAD BASMA |
| Quality Review Completed | 12/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/3/2023 | JAD BASMA |
| Plan Check Approved | 5/18/2023 | JAD BASMA |
| Issued | 8/1/2023 | APPLICANT |
| CofO in Progress | 12/20/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
| CofO Issued | 1/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/1/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 12/9/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 12/21/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | COLIN LOREDO |
| ZI | Cleared | 1/11/2023 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 2/13/2023 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 4/26/2023 | ADALBERTO VERA |
| Permit | Cleared | 4/27/2023 | NIKKI ZULUETA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO,, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2023 | Corrections Issued | MANUEL TEJADA |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | CRAIG DAVIS |
| Underground Mechanical | 1/12/2024 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 1/18/2024 | Approved | KIRK SANDERS |
| Deputy Reinf. Concrete | 1/19/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Partial Approval | KIRK SANDERS |
| Pre-Inspection | 2/28/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 3/7/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/11/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/14/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 3/14/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 3/14/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/21/2024 | Partial Approval | KIRK SANDERS |
| Pre-Inspection | 3/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 4/3/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 4/3/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 4/3/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 4/3/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/10/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 4/18/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 7/22/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 8/5/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/18/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/2/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 10/17/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 11/7/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/15/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 12/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 12/19/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | CHRISTOPHER ROJAS |