6537 1/2 N VALJEAN AVE 91406

Certificate Information: 6537 1/2 N VALJEAN AVE 91406

Application / Permit
22010-20000-05629
Plan Check / Job No.
B22VN17072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (31'-6"x40'-0"), 1190 SQFT 1-STORY DETACHED SINGLE FAMILY DWELLING PER SB9 W/NFPA 13R SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 PETER MOSESIAN
Corrections Issued 11/26/2022 PETER MOSESIAN
Quality Review Completed 12/1/2022 OMID HEDAYAT
Building Plans Picked Up 12/15/2022 APPLICANT
Plan Check Approved 8/21/2023 PETER MOSESIAN
Issued 9/7/2023 APPLICANT
CofO in Progress 1/16/2026 GAREN HAYRAPETYAN
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 2/9/2023 KURT CORRAL
Low Impact Development Cleared 5/26/2023 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 6/7/2023 MEGAN GODINEZ
Sewer availability Cleared 6/7/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/8/2023 MEGAN GODINEZ
Senate Bill 9 Cleared 8/14/2023 STEVEN WECHSLER
ZI Cleared 8/14/2023 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 5/6/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/6/2024 Partial Approval RAUL OLAGI
Deputy Reinf. Concrete 5/7/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/10/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/18/2024 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 9/18/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 12/23/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 12/23/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 12/23/2024 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 12/23/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 1/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 1/21/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 1/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 1/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 1/23/2025 Partial Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/23/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/27/2025 Partial Approval SALVADOR MARTINEZ
HVAC-Rough 1/27/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 1/27/2025 Approved SALVADOR MARTINEZ
Insulation 2/3/2025 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 3/10/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 3/10/2025 Approved SALVADOR MARTINEZ
Shower Pan 3/10/2025 Approved SALVADOR MARTINEZ
Pre-Inspection 6/3/2025 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/30/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 10/2/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 12/3/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/10/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/10/2025 Approved GAREN HAYRAPETYAN
Final 12/10/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/10/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 12/10/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 12/10/2025 Approved GAREN HAYRAPETYAN
Final 1/9/2026 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 1/9/2026 Not Ready for Inspection RYAN SALAZAR
Final 1/16/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 1/16/2026 Approved GAREN HAYRAPETYAN