8132 N RHODES AVE 91605
Certificate Information: 8132 N RHODES AVE 91605
- Application / Permit
- 22010-20000-05603
- Plan Check / Job No.
- B22VN17025
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW SINGLE-STORY 20'-6" x 43' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | LUIS RINCON |
| Corrections Issued | 11/19/2022 | LUIS RINCON |
| Building Plans Picked Up | 12/16/2022 | APPLICANT |
| Issued | 3/14/2023 | APPLICANT |
| CofO in Progress | 7/25/2024 | MATTHEW NELSON |
| CofO in Progress | 9/6/2024 | MATTHEW NELSON |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/31/2023 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 2/10/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 3/5/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/9/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/13/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 9/6/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/13/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 10/27/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 10/27/2023 | Approved | WILLIAM WREN |
| Wood Frame | 10/27/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 1/5/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 1/5/2024 | Corrections Issued | MATTHEW NELSON |
| Shower Pan | 1/5/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/17/2024 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 1/17/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/17/2024 | Approved | MATTHEW NELSON |
| Insulation | 1/26/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/9/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/9/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/9/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | MATTHEW NELSON |
| Final | 6/11/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 6/11/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 6/11/2024 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 6/11/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 6/11/2024 | Approved | MATTHEW NELSON |
| Final | 6/20/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Final | 6/20/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 6/20/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 7/1/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 7/1/2024 | Approved | MATTHEW NELSON |
| Final | 7/17/2024 | OK to Issue CofO | MATTHEW NELSON |