10822 N AQUEDUCT AVE 91344
Certificate Information: 10822 N AQUEDUCT AVE 91344
- Application / Permit
- 22010-20000-05601
- Plan Check / Job No.
- B22VN17014
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 25'X18' ACCESSORY DWELLING UNIT PER LAMC 12.22.A33(c) & (d). ALL WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 11/19/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/22/2022 | APPLICANT |
| Issued | 3/30/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | JAVIER RAMOS JR |
| CofO Issued | 4/18/2024 | RUBEN SALAS |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/28/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/29/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/20/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 3/24/2023 | RIDWAN HARDY |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2023 | Partial Approval | MICHEL ABAJAN |
| Sewer | 4/10/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 4/10/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/13/2023 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/12/2023 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | JOHN COLEMAN |
| MERV13>=Rough | 5/12/2023 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 5/12/2023 | OK to Expire Permit | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 5/12/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/17/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 5/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/17/2023 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 5/17/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 5/17/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 5/17/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/31/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/31/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 5/31/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/7/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/7/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/7/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 3/7/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 3/7/2024 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 3/7/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/7/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/7/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/15/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 4/15/2024 | Approved | JAVIER RAMOS JR |