415 N FORMOSA AVE 90036

Certificate Information: 415 N FORMOSA AVE 90036

Application / Permit
22010-20000-05589
Plan Check / Job No.
B22VN16981
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED REC ROOM
Permit Issued
Issued on 1/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 SELLA BENYAMIN
Corrections Issued 11/28/2022 SELLA BENYAMIN
Quality Review Completed 11/30/2022 STEVEN KIM
Building Plans Picked Up 11/30/2022 APPLICANT
Plan Check Approved 1/26/2023 SELLA BENYAMIN
Issued 1/26/2023 APPLICANT
CofO in Progress 1/31/2025 JOSE MACIAS
No Progress 2/10/2025 JOAQUIN GREENOUGH
CofO in Progress 2/10/2025 JOAQUIN GREENOUGH
No Progress 5/15/2025 DEROLD HAUFF
CofO in Progress 5/15/2025 DEROLD HAUFF
CofO in Progress 5/20/2025 JOSE MACIAS
CofO in Progress 5/28/2025 RAUL BARAJAS
Permit Finaled 5/29/2025 DEROLD HAUFF
CofO Issued 5/29/2025 DEROLD HAUFF
Permit Finaled 5/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2022 CINDY QI
Construction near power lines Cleared 12/29/2022 WALTER RAMIREZ
Low Impact Development Cleared 1/11/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/11/2023 CINDY QI

Contact Information

Contractor David Elliot Builders Inc; Lic. No.: 1021000-B 5967 W 3RD STREET      LOS ANGELES, CA 90036

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/2/2023 Partial Approval LILIANA PORTILLO
METHANE-Subgrade 5/2/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 5/2/2023 Partial Approval LILIANA PORTILLO
Sewer 5/2/2023 Approved LILIANA PORTILLO
Underground Mechanical 5/2/2023 Partial Approval LILIANA PORTILLO
METHANE-Subgrade 6/1/2023 Approved LILIANA PORTILLO
Deputy Methane Barrier 6/6/2023 Approved LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 6/7/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 6/7/2023 Approved LILIANA PORTILLO
METHANE-Barrier 6/7/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/19/2023 Approved LILIANA PORTILLO
HVAC-Rough 12/19/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 12/19/2023 Approved LILIANA PORTILLO
Underground Mechanical 12/19/2023 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 1/22/2024 Conditional Approval LILIANA PORTILLO
Green Building Rough 1/22/2024 Not Ready for Inspection LILIANA PORTILLO
METHANE-Rough 1/22/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 1/22/2024 Approved LILIANA PORTILLO
Insulation 2/16/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 2/16/2024 Not Ready for Inspection AMIR NAZARIAN
Shower Pan 2/16/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 2/21/2024 Partial Approval AMIR NAZARIAN
Drywall Nailing 2/29/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 2/29/2024 Approved AMIR NAZARIAN
Verify Rec and Parks Fee Memo 5/30/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Final 1/14/2025 Approved JOSE MACIAS
HVAC-Final 1/14/2025 Approved JOSE MACIAS
PLUMBING-Final 1/14/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 1/27/2025 Approved JOSE MACIAS
Final 1/27/2025 Not Ready for Inspection JOSE MACIAS
Green Building Final 1/27/2025 Approved JOSE MACIAS
Green Building Rough 1/27/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved JOSE MACIAS
Service/Power Release 1/27/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 1/27/2025 Approved JOSE MACIAS
Final 1/30/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 1/30/2025 Approved JOSE MACIAS
Special/Order Compliance 2/10/2025 Corrections Issued JOAQUIN GREENOUGH
Final 5/8/2025 Corrections Issued RAUL BARAJAS
Final 5/20/2025 OK to Issue CofO JOSE MACIAS