22827 W BURTON ST 91304
Certificate Information: 22827 W BURTON ST 91304
- Application / Permit
- 22010-20000-05581
- Plan Check / Job No.
- B22VN16937
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 800 sq. ft Single Family Dwelling Unit per SB9 Two unit Development Ca Goct Code 65852.21
- Permit Issued
- Issued on 7/3/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | HERNAN ARREOLA |
| Corrections Issued | 12/12/2022 | HERNAN ARREOLA |
| Quality Review Completed | 12/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 6/23/2023 | HERNAN ARREOLA |
| Issued | 7/3/2023 | APPLICANT |
| CofO in Progress | 12/31/2024 | JEFFREY HARTLINE |
| CofO in Progress | 1/22/2025 | SEAN WIRCH |
| CofO in Progress | 2/26/2025 | JEFFREY HARTLINE |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
| CofO Issued | 3/6/2025 | JOHN JANSON |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/16/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 5/29/2023 | ANTHONY VARGAS |
| Construction within easement | Cleared | 5/30/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/30/2023 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 6/1/2023 | COLIN LOREDO |
Contact Information
| Contractor | Coasis Construction & Remodeling Inc; Lic. No.: 1099824-B | 9532 TOPANGA CANYON BLVD CHATSWORTH, CA 91311 |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: NA93095 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/28/2023 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/6/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/23/2023 | Corrections Issued | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/23/2023 | Approved | JEFFREY HARTLINE |
| Wood Frame | 10/23/2023 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 11/2/2023 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 11/2/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 11/13/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 11/13/2023 | Corrections Issued | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/8/2023 | Approved | JEFFREY HARTLINE |
| Sewer | 2/21/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 2/21/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/8/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 3/8/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/8/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 3/12/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 3/21/2024 | Approved | HENRY KIM |
| Shower Pan | 4/18/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 4/25/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 5/2/2024 | Partial Approval | JEFFREY HARTLINE |
| Sewer | 7/3/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 7/3/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 8/8/2024 | Approved | JEFFREY HARTLINE |
| Final | 8/8/2024 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 8/8/2024 | Approved | JEFFREY HARTLINE |
| Green Building Final | 8/8/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 8/8/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 8/8/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 8/8/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 8/8/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 8/8/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 11/13/2024 | Approved | JEFFREY HARTLINE |
| Final | 11/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 11/13/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 11/13/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 11/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 11/20/2024 | Approved | JEFFREY HARTLINE |
| Final | 11/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 11/20/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 11/20/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 11/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Special/Order Compliance | 11/20/2024 | Partial Approval | JEFFREY HARTLINE |
| Final | 12/10/2024 | Corrections Issued | JEFFREY HARTLINE |
| Service/Power Release | 12/10/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 12/24/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Service/Power Release | 12/24/2024 | Approved | JEFFREY HARTLINE |
| Final | 12/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/30/2024 | Approved | JEFFREY HARTLINE |
| Final | 12/30/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 12/30/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/30/2024 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/30/2024 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 1/17/2025 | Corrections Issued | JEFFREY HARTLINE |
| Final | 2/5/2025 | OK to Issue CofO | JEFFREY HARTLINE |