8058 N RADFORD AVE 91605
Certificate Information: 8058 N RADFORD AVE 91605
- Application / Permit
- 22010-20000-05562
- Plan Check / Job No.
- B22VN16869
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULARLY SHAPED 22'6" x 42' ACCESSORY DWELLING UNIT (756 SF) PER LAMC 12.22 A.33(c) AND (d). DESIGN BY WFPP.
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2022 | LUIS RINCON |
| Corrections Issued | 11/15/2022 | LUIS RINCON |
| Building Plans Picked Up | 11/29/2022 | APPLICANT |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 7/2/2024 | MATTHEW NELSON |
| CofO Issued | 7/22/2024 | RUBEN SALAS |
| Permit Finaled | 7/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 3/5/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/18/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | DAGOVERTO GUERRERO |
| ZI | Cleared | 4/24/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/27/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/12/2023 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 10/19/2023 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 10/20/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 12/4/2023 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 12/4/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/16/2024 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 1/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 1/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 1/25/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/7/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/8/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/8/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/8/2024 | Approved | MATTHEW NELSON |
| Insulation | 2/21/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/27/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 3/5/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/12/2024 | Approved | MATTHEW NELSON |
| Final | 5/7/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 5/7/2024 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Not Ready | JOHN COLEMAN |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 5/7/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 5/13/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 5/13/2024 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 5/13/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 5/13/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 5/29/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 5/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 5/29/2024 | Approved | MATTHEW NELSON |
| Final | 6/7/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 6/7/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 6/7/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 6/26/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 6/26/2024 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 6/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 7/1/2024 | Partial Inspection | MATTHEW NELSON |
| Final | 7/2/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 7/2/2024 | Approved | MATTHEW NELSON |
| Service/Power Release | 7/2/2024 | Approved | MATTHEW NELSON |