20140 W RINALDI ST 91326
Certificate Information: 20140 W RINALDI ST 91326
- Application / Permit
- 22010-20000-05542
- Plan Check / Job No.
- B22VN16831
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- (N) 1-STORY TYPE V-B CORE & SHELL S9 RESTAURANT AND RETAIL PER CPC-2016-837-SP-MCUP-DRB-SPP-SPR
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- CofO Corrected on 4/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | HERNAN ARREOLA |
| Corrections Issued | 11/30/2022 | HERNAN ARREOLA |
| Quality Review Completed | 12/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/4/2023 | HERNAN ARREOLA |
| Plan Check Approved | 1/2/2024 | HERNAN ARREOLA |
| Issued | 1/22/2025 | APPLICANT |
| CofO in Progress | 2/19/2026 | GREGORY POMISH |
| CofO Issued-Status Void | 3/10/2026 | RICKEY JACKSON |
| Permit Finaled-Status Void | 3/10/2026 | RICKEY JACKSON |
| Re-Activate Permit | 4/15/2026 | JEFFREY DURAN |
| Permit Finaled | 4/15/2026 | JEFFREY DURAN |
| CofO Corrected | 4/15/2026 | JEFFREY DURAN |
| Permit Finaled | 4/15/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| "D" conditions | Cleared | 12/28/2022 | KENTON TRINH |
| "T" removal | Cleared | 12/28/2022 | KENTON TRINH |
| Address approval | Cleared | 12/28/2022 | LEE GUILBEAUX |
| Highway dedication | Cleared | 12/28/2022 | LEE GUILBEAUX |
| Permit | Cleared | 12/28/2022 | LEE GUILBEAUX |
| Specific Plan | Cleared | 12/28/2022 | KENTON TRINH |
| ZA Case | Cleared | 12/28/2022 | KENTON TRINH |
| Sewer availability | Cleared | 1/9/2023 | LEE GUILBEAUX |
| Green Code | Cleared | 1/11/2023 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2023 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 10/18/2023 | Shangqin Xie |
| Grading Pre-Inspection | Cleared | 11/20/2023 | MICHAEL TEMPLE |
| Hydrant and Access approval | Cleared | 12/6/2023 | RUEL COLE |
| Food Service Establishment | Cleared | 12/19/2023 | RAMESHBHAIR PATEL |
| GPI Written Notices | Cleared | 1/2/2024 | HERNAN ARREOLA |
Contact Information
| Architect | Rose,, Hugh Mason; Lic. No.: NA30461 | , |
| Contractor | Moorefield Construction Inc; Lic. No.: 397892-B | , |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/20/2025 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 2/21/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 2/24/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Rough | 4/8/2025 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 4/8/2025 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 4/8/2025 | Not Ready for Inspection | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 4/29/2025 | Partial Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 5/9/2025 | Approved | GREGORY POMISH |
| Insulation | 5/16/2025 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 5/19/2025 | Not Ready for Inspection | GREGORY POMISH |
| Insulation | 5/19/2025 | Not Ready for Inspection | GREGORY POMISH |
| Insulation | 5/20/2025 | Approved | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 6/6/2025 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 6/6/2025 | Partial Inspection | GREGORY POMISH |
| Drywall Nailing | 6/11/2025 | Approved | DANIEL VARNUM |
| Green Building Rough | 6/11/2025 | Approved | DANIEL VARNUM |
| Light Gage Steel Frame | 8/14/2025 | Partial Approval | ROBERT DAVIS |
| Final | 1/22/2026 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 1/22/2026 | Approved | GREGORY POMISH |
| Green Building Final | 1/22/2026 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Not Ready | GREGORY POMISH |
| Smoke Detectors | 1/22/2026 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 1/22/2026 | Approved | GREGORY POMISH |
| Wood Frame | 1/22/2026 | Approved | GREGORY POMISH |
| Final | 1/28/2026 | OK to Issue CofO | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | GREGORY POMISH |