17318 W BIRCHER ST 91344
Certificate Information: 17318 W BIRCHER ST 91344
- Application / Permit
- 22010-20000-05530
- Plan Check / Job No.
- B22VN16798
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR SHAPED (40'-6"x47'-4"), 1200 SQFT 1-STORY ADU W/ATTACHED 1-CAR GARAGE (272 SQFT) PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- Current Status
- CofO Issued on 1/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | PETER MOSESIAN |
| Corrections Issued | 1/8/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/11/2023 | OMID HEDAYAT |
| Plan Check Approved | 3/29/2023 | PETER MOSESIAN |
| Issued | 3/29/2023 | APPLICANT |
| CofO in Progress | 1/5/2024 | STEVEN BACK |
| Permit Finaled | 1/16/2024 | JOHN JANSON |
| CofO Issued | 1/16/2024 | JOHN JANSON |
| Permit Finaled | 1/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 2/23/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 2/28/2023 | COLIN LOREDO |
| Low Impact Development | Cleared | 3/1/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/2/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2023 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/26/2023 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 4/26/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 5/10/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 5/19/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 5/19/2023 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/19/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/24/2023 | Partial Approval | STEVEN BACK |
| Shower Pan | 5/24/2023 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 5/30/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 6/1/2023 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 6/2/2023 | Approved | STEVEN BACK |
| Drywall Nailing | 6/5/2023 | Approved | DAVID SCANTLIN |
| Insulation | 6/5/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/14/2023 | Approved | STEVEN BACK |
| Underground Mechanical | 7/27/2023 | Approved | HORACE FULTZ |
| Pre-Inspection | 12/4/2023 | Partial Inspection | STEVEN BACK |
| Final | 12/18/2023 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 12/18/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 1/5/2024 | Approved | STEVEN BACK |
| Final | 1/5/2024 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 1/5/2024 | Approved | STEVEN BACK |
| PLUMBING-Final | 1/5/2024 | Approved | STEVEN BACK |
| Service/Power Release | 1/5/2024 | Approved | STEVEN BACK |