4846 N AGNES AVE 91607
Certificate Information: 4846 N AGNES AVE 91607
- Application / Permit
- 22010-20000-05520
- Plan Check / Job No.
- B22VN15874
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW DETACHED REC ROOM AT REAR
- Permit Issued
- Issued on 2/1/2023
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | JOE VO |
| Corrections Issued | 11/12/2022 | JOE VO |
| Quality Review Completed | 11/16/2022 | GARO TELMI |
| Plan Check Approved | 1/10/2023 | JOE VO |
| Issued | 2/1/2023 | APPLICANT |
| CofO in Progress | 11/3/2023 | JOHN COLEMAN |
| Permit Finaled | 12/18/2023 | RUBEN SALAS |
| CofO Issued | 12/18/2023 | RUBEN SALAS |
| Permit Finaled | 12/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/12/2022 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/15/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 11/22/2022 | JOANNA MARROQUIN |
| Low Impact Development | Cleared | 12/15/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 1/10/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/3/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/16/2023 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 5/16/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 5/16/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/23/2023 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 5/23/2023 | Approved | JACK KARGODORIAN |
| Insulation | 5/26/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 6/1/2023 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 6/1/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/2/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 6/2/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 6/6/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/29/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 10/2/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 10/2/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JOHN COLEMAN |
| Final | 11/2/2023 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 11/2/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 11/2/2023 | Approved | JOHN COLEMAN |
| Smoke Detectors | 11/2/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | JOHN COLEMAN |