12734 W GAULT ST 91605

Certificate Information: 12734 W GAULT ST 91605

Application / Permit
22010-20000-05500
Plan Check / Job No.
B22VN16730
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (N) PROPOSED 2 STORY DETACHED ADU
Permit Issued
Issued on 9/26/2023
Issuing Office
Current Status
Issued on 9/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/10/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 CRYSTEL MAALOUF
Corrections Issued 12/15/2022 CRYSTEL MAALOUF
Quality Review Completed 12/21/2022 GARO TELMI
Plan Check Approved 9/25/2023 CRYSTEL MAALOUF
Issued 9/26/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/23/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/15/2023 CARLOS AGUILERA
Sewer availability Cleared 8/15/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/23/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/29/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 11/29/2023 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 11/29/2023 Not Ready for Inspection KIRK SANDERS
Deputy Drilled-In Anchors 11/30/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/5/2023 Approved JOSE AVILA
PLUMBING-Rough 12/5/2023 Partial Approval JOSE AVILA
Deputy Wood Construction 8/30/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 9/6/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 9/9/2024 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/17/2025 No Access for Inspection OGANES TARAKHCHYAN
HVAC-Rough 1/17/2025 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/17/2025 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/22/2025 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/22/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 1/22/2025 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 2/19/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/11/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/17/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/7/2025 Conditional Approval GAREN HAYRAPETYAN
Green Building Rough 8/7/2025 Approved GAREN HAYRAPETYAN
Insulation 8/12/2025 No Access for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/14/2025 Approved GAREN HAYRAPETYAN
Insulation 8/14/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 8/14/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 8/21/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/30/2025 Approved WAYNE REGESTER