316 E 98TH ST 90003

Certificate Information: 316 E 98TH ST 90003

Application / Permit
22010-20000-05491
Plan Check / Job No.
B22VN16706
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31' X 18'-6" TWO STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g) WITH ATTACHED PATIO COVER AND TRELLIS
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 SELLA BENYAMIN
Corrections Issued 11/22/2022 SELLA BENYAMIN
Quality Review Completed 11/30/2022 STEVEN KIM
Building Plans Picked Up 12/6/2022 APPLICANT
Applicant returned to address corrections 3/31/2023 SELLA BENYAMIN
Plan Check Approved 4/25/2023 SELLA BENYAMIN
Issued 4/25/2023 APPLICANT
CofO in Progress 1/10/2024 JOHN KLARIN
Permit Finaled 1/10/2024 ANSON MAGLASANG
CofO Issued 1/10/2024 ANSON MAGLASANG
Permit Finaled 1/10/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/28/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/28/2022 CELINA MORENO
Construction near power lines Cleared 3/10/2023 RIDWAN HARDY
Low Impact Development Cleared 3/16/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/17/2023 CELINA MORENO
Sewer availability Cleared 3/23/2023 CELINA MORENO

Contact Information

Contractor La Green Development Inc; Lic. No.: 1061369-B 15260 VENTURA BLVD 840      SHERMAN OAKS, CA 91403
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 5/16/2023 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 5/18/2023 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 5/22/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Corrections Issued JOHN KLARIN
HVAC-Rough 6/7/2023 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 6/7/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 6/7/2023 Not Ready for Inspection JOHN KLARIN
Shower Pan 6/7/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 6/9/2023 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 6/9/2023 Not Ready for Inspection JOHN KLARIN
Rough-Elec/Plmb/HVAC 6/9/2023 Corrections Issued JOHN KLARIN
Shower Pan 6/9/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 6/13/2023 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 6/13/2023 Approved JOHN KLARIN
Shower Pan 6/13/2023 Approved JOHN KLARIN
HVAC-Rough 6/22/2023 Approved JOHN KLARIN
Insulation 6/22/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 6/22/2023 Approved JOHN KLARIN
Sewer 6/22/2023 Approved JOHN KLARIN
Shower Pan 6/22/2023 Approved JOHN KLARIN
Wood Frame 6/22/2023 Approved JOHN KLARIN
Drywall Nailing 6/30/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 6/30/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 7/10/2023 Approved JOHN KLARIN
Pre-Inspection 7/10/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/27/2023 Approved JOHN KLARIN
Final 7/27/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/27/2023 Corrections Issued JOHN KLARIN
Green Building Rough 7/27/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 7/27/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 7/27/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/27/2023 Approved JOHN KLARIN
Final 8/3/2023 Corrections Issued JOHN KLARIN
Green Building Final 8/3/2023 Approved JOHN KLARIN
Service/Power Release 8/3/2023 Not Ready for Inspection JOHN KLARIN
Final 8/14/2023 Corrections Issued JOHN KLARIN
Service/Power Release 8/14/2023 Not Ready for Inspection JOHN KLARIN
Final 11/17/2023 Corrections Issued JOHN KLARIN
Service/Power Release 11/17/2023 Not Ready for Inspection JOHN KLARIN
Final 11/28/2023 Corrections Issued JOHN KLARIN
Service/Power Release 11/28/2023 Corrections Issued JOHN KLARIN
Final 1/4/2024 Corrections Issued JOHN KLARIN
Service/Power Release 1/4/2024 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 1/10/2024 Approved JOHN KLARIN
Final 1/10/2024 OK to Issue CofO JOHN KLARIN
HVAC-Final 1/10/2024 Approved JOHN KLARIN
PLUMBING-Final 1/10/2024 Approved JOHN KLARIN
Service/Power Release 1/10/2024 Approved JOHN KLARIN