316 E 98TH ST 90003
Certificate Information: 316 E 98TH ST 90003
- Application / Permit
- 22010-20000-05491
- Plan Check / Job No.
- B22VN16706
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31' X 18'-6" TWO STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g) WITH ATTACHED PATIO COVER AND TRELLIS
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 11/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 11/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/6/2022 | APPLICANT |
| Applicant returned to address corrections | 3/31/2023 | SELLA BENYAMIN |
| Plan Check Approved | 4/25/2023 | SELLA BENYAMIN |
| Issued | 4/25/2023 | APPLICANT |
| CofO in Progress | 1/10/2024 | JOHN KLARIN |
| Permit Finaled | 1/10/2024 | ANSON MAGLASANG |
| CofO Issued | 1/10/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/10/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2022 | CELINA MORENO |
| Construction near power lines | Cleared | 3/10/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/16/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/17/2023 | CELINA MORENO |
| Sewer availability | Cleared | 3/23/2023 | CELINA MORENO |
Contact Information
| Contractor | La Green Development Inc; Lic. No.: 1061369-B | 15260 VENTURA BLVD 840 SHERMAN OAKS, CA 91403 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 5/16/2023 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 5/22/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 6/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 6/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 6/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| Shower Pan | 6/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/9/2023 | Corrections Issued | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 6/9/2023 | Not Ready for Inspection | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 6/9/2023 | Corrections Issued | JOHN KLARIN |
| Shower Pan | 6/9/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/13/2023 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 6/13/2023 | Approved | JOHN KLARIN |
| Shower Pan | 6/13/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 6/22/2023 | Approved | JOHN KLARIN |
| Insulation | 6/22/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/22/2023 | Approved | JOHN KLARIN |
| Sewer | 6/22/2023 | Approved | JOHN KLARIN |
| Shower Pan | 6/22/2023 | Approved | JOHN KLARIN |
| Wood Frame | 6/22/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/30/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/30/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/10/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 7/10/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/27/2023 | Approved | JOHN KLARIN |
| Final | 7/27/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/27/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 7/27/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/27/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/27/2023 | Approved | JOHN KLARIN |
| Final | 8/3/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/3/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 8/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 8/14/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 8/14/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/17/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 11/17/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/28/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 11/28/2023 | Corrections Issued | JOHN KLARIN |
| Final | 1/4/2024 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 1/4/2024 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 1/10/2024 | Approved | JOHN KLARIN |
| Final | 1/10/2024 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 1/10/2024 | Approved | JOHN KLARIN |
| PLUMBING-Final | 1/10/2024 | Approved | JOHN KLARIN |
| Service/Power Release | 1/10/2024 | Approved | JOHN KLARIN |