20732 W PARTHENIA ST 91306

Certificate Information: 20732 W PARTHENIA ST 91306

Application / Permit
22010-20000-05490
Plan Check / Job No.
B22VN16701
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (25'-0"x45'-0"), 1056 SQFT ACCESSORY DWELLING UNIT PER LAMC 1222. A. 33 (c)(d) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/30/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 PETER MOSESIAN
Corrections Issued 11/29/2022 PETER MOSESIAN
Quality Review Completed 12/6/2022 OMID HEDAYAT
Building Plans Picked Up 12/9/2022 APPLICANT
Plan Check Approved 6/23/2023 PETER MOSESIAN
Issued 6/30/2023 APPLICANT
CofO in Progress 1/29/2026 JEFFREY HARTLINE
Permit Finaled 2/12/2026 JOHN JANSON
CofO Issued 2/12/2026 JOHN JANSON
Permit Finaled 2/12/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/12/2023 CARLOS AGUILERA
Trees in Parkway Cleared 1/30/2023 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 1/31/2023 ROSE MARIE SMITH
Senate Bill 9 Cleared 3/8/2023 STEVEN WECHSLER
Hydrant and Access approval Cleared 4/18/2023 MATTHEW CRAIG
Low Impact Development Cleared 5/2/2023 LUIS LUVANO
Permit Cleared 5/3/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/3/2023 CARLOS AGUILERA
Sewer availability Cleared 6/14/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/12/2023 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Approved JEFFREY HARTLINE
Green Building Rough 12/12/2023 Not Ready for Inspection JEFFREY HARTLINE
Verify Sprinkler Sign Off 12/12/2023 Corrections Issued JEFFREY HARTLINE
Wood Frame 12/12/2023 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Approved JEFFREY HARTLINE
HVAC-Rough 12/15/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/15/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/22/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/22/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/22/2024 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 1/22/2024 Approved JEFFREY HARTLINE
Insulation 1/24/2024 Approved JEFFREY HARTLINE
Drywall Nailing 1/31/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/7/2024 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 2/9/2024 Partial Approval JEFFREY HARTLINE
Service/Power Release 6/6/2025 Approved JEFFREY HARTLINE
Final 10/30/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 10/30/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Required JEFFREY HARTLINE
Smoke Detectors 10/30/2025 Approved JEFFREY HARTLINE
Final 12/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 12/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 1/29/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 1/29/2026 Approved JEFFREY HARTLINE