4442 N BEN AVE 91607

Certificate Information: 4442 N BEN AVE 91607

Application / Permit
22010-20000-05486
Plan Check / Job No.
B22VN16700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- NEW 2-STORY SFD WITH A NEW ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/27/2023
Issuing Office
Current Status
CofO Issued on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 MAHNAZ NOURHASHEMI
Corrections Issued 11/25/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 12/2/2022 GARO TELMI
Applicant returned to address corrections 5/10/2023 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 5/22/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 6/5/2023 MAHNAZ NOURHASHEMI
Issued 7/27/2023 APPLICANT
CofO in Progress 12/20/2024 CHRISTOPHER ROJAS
Permit Finaled 1/7/2025 RUBEN SALAS
CofO Issued 1/7/2025 RUBEN SALAS
Permit Finaled 1/7/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/1/2022 COLIN LOREDO
Permit Cleared 12/1/2022 COLIN LOREDO
Sewer availability Cleared 12/1/2022 COLIN LOREDO
Address approval Cleared 12/8/2022 COLIN LOREDO
Hydrant and Access approval Cleared 12/17/2022 KURT CORRAL
ZI Cleared 1/11/2023 MIGUEL GAMBOA
Trees in Parkway Cleared 2/13/2023 ADALBERTO VERA
Low Impact Development Cleared 2/22/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/23/2023 JOHN LIN
Disturb/Remove Protected Trees Cleared 4/26/2023 ADALBERTO VERA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 200      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/23/2023 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 1/12/2024 Partial Approval CRAIG DAVIS
Underground Mechanical 1/12/2024 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/18/2024 Approved KIRK SANDERS
Footing/Foundation/Slab 1/18/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval KIRK SANDERS
Deputy Wood Construction 2/27/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Partial Approval KIRK SANDERS
Pre-Inspection 2/28/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 3/7/2024 Approved KIRK SANDERS
ELECTRICAL-Rough 3/11/2024 Approved JOHN COLEMAN
Shower Pan 3/14/2024 Approved DAVID ANDERSON
Deputy Wood Construction 3/19/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 3/21/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/2/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 4/2/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 4/2/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/2/2024 Partial Approval CHRISTOPHER ROJAS
MERV13>=Rough 4/2/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 4/2/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/10/2024 Approved CHRISTOPHER ROJAS
Insulation 4/16/2024 Approved MISAEL ESPARZA
Drywall Nailing 4/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/9/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/16/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 8/16/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 8/16/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 8/21/2024 Approved CHRISTOPHER ROJAS
Gas Test 8/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 8/21/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 9/5/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 9/10/2024 Approved MISAEL ESPARZA
Service/Power Release 11/8/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 11/15/2024 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/19/2024 Approved CHRISTOPHER ROJAS
Final 12/19/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 12/19/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 12/19/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 12/19/2024 Approved CHRISTOPHER ROJAS