4709 N DEL MORENO DR 91364

Certificate Information: 4709 N DEL MORENO DR 91364

Application / Permit
22010-20000-05485
Plan Check / Job No.
B22VN16697
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY CALIFORNIA DEPARTMENT OF HOUSING AND COMMUNITY DEVELOPMENT APPROVED FACTORY BUILT ACCESSORY DWELLING UNIT ***A supplemental permit to install Solar Photovoltaic Panels, or approval from HCD exempting the unit from Solar Photovoltaic installation is required prior to obtaining Certificate of Occupancy
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 DANIEL YIP
Corrections Issued 11/18/2022 DANIEL YIP
Applicant returned to address corrections 5/2/2023 DANIEL YIP
Plan Check Approved 8/30/2023 DANIEL SANJUAN
Issued 8/30/2023 APPLICANT
CofO in Progress 2/2/2024 JOHN KIDWELL
Permit Finaled 2/6/2024 JOHN JANSON
CofO Issued 2/6/2024 JOHN JANSON
Permit Finaled 2/6/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/6/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/9/2022 CARLOS AGUILERA
Sewer availability Cleared 12/9/2022 CARLOS AGUILERA
GPI Written Notices Cleared 5/3/2023 DANIEL YIP
Grading Pre-Inspection Cleared 5/3/2023 DANIEL YIP
Low Impact Development Cleared 8/24/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 8/26/2023 CARLOS AGUILERA

Contact Information

Contractor Abodu Inc; Lic. No.: 1073522-B       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2023 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 10/24/2023 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 10/25/2023 Approved PETER FOLLING
ELECTRICAL-Rough 11/6/2023 Approved PETER FOLLING
Sewer 11/6/2023 Approved PETER FOLLING
Underground Mechanical 11/6/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 12/13/2023 Approved JOHN KIDWELL
Drywall Nailing 12/13/2023 Approved JOHN KIDWELL
Final 12/13/2023 Corrections Issued JOHN KIDWELL
Green Building Final 12/13/2023 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 12/13/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Not Required JOHN KIDWELL
Service/Power Release 12/13/2023 Approved JOHN KIDWELL
Smoke Detectors 12/13/2023 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/13/2023 Approved JOHN KIDWELL
Final 1/4/2024 Not Ready for Inspection MORRIS JACKSON
Green Building Final 1/4/2024 Corrections Issued MORRIS JACKSON
Final 2/1/2024 OK to Issue CofO JOHN KIDWELL
Green Building Final 2/1/2024 Approved JOHN KIDWELL