13502 W ERWIN ST 91401
Certificate Information: 13502 W ERWIN ST 91401
- Application / Permit
- 22010-20000-05448
- Plan Check / Job No.
- B22VN16570
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 4,429 S.F. (61' x 50') 2-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 2 CAR GARAGE (397S.F.) . NFPA-13D FIRE SPRINKLER IS REQUIRED.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 1/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | NGHI SU |
| Corrections Issued | 12/5/2022 | NGHI SU |
| Quality Review Completed | 12/7/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/2/2023 | NGHI SU |
| Plan Check Approved | 8/4/2023 | NGHI SU |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 11/20/2025 | WAYNE REGESTER |
| Permit Finaled | 1/6/2026 | RUBEN SALAS |
| CofO Issued | 1/6/2026 | RUBEN SALAS |
| Permit Finaled | 1/6/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/24/2023 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 3/6/2023 | COLIN LOREDO |
| Low Impact Development | Cleared | 4/7/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 7/26/2023 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 7/26/2023 | ADALBERTO VERA |
Contact Information
| Architect | Sadekyan,, Hamlet; Lic. No.: C39815 | 1950 CHILTON DR GLENDALE, CA 91201 |
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/28/2023 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 9/5/2023 | Approved | KIRK SANDERS |
| Deputy Reinf. Concrete | 9/7/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 10/26/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/12/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 2/12/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/20/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/20/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 2/20/2024 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 2/20/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/20/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 2/20/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 3/6/2024 | No Access for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 3/6/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/11/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 3/11/2024 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/14/2024 | Approved | JOSE AVILA |
| Green Building Rough | 3/14/2024 | Approved | JOSE AVILA |
| Insulation | 3/19/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 4/24/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 4/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/14/2024 | Partial Approval | SALVADOR MARTINEZ |
| Shower Pan | 5/14/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/21/2024 | Approved | LEONARD ROSS II |
| Sewer | 10/17/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/22/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/3/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 11/3/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 11/3/2025 | Approved | WAYNE REGESTER |
| Final | 11/7/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 11/7/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Service/Power Release | 11/7/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 11/7/2025 | Approved | WAYNE REGESTER |
| Final | 11/19/2025 | OK to Issue CofO | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Approved | WAYNE REGESTER |