17859 W WILLARD ST 91335

Certificate Information: 17859 W WILLARD ST 91335

Application / Permit
22010-20000-05447
Plan Check / Job No.
B22VN16565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 20' x 25'-9" ONE-STORY SINGLE FAMILY DWELLING PER SB9; ALL WORK PER WFPP AND ENGINEERING DESIGN; NFPA-13D THRU-OUT
Permit Issued
Issued on 8/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 SEAN SHAHMIRI
Corrections Issued 11/14/2022 SEAN SHAHMIRI
Quality Review Completed 11/16/2022 OMID HEDAYAT
Building Plans Picked Up 11/17/2022 APPLICANT
Plan Check Approved 8/2/2023 SEAN SHAHMIRI
Issued 8/15/2023 APPLICANT
CofO in Progress 6/25/2024 JEFFREY BULL
Permit Finaled 9/3/2024 JOHN JANSON
CofO Issued 9/3/2024 JOHN JANSON
Permit Finaled 9/3/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/17/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/17/2022 LEE GUILBEAUX
Sewer availability Cleared 11/17/2022 LEE GUILBEAUX
Construction within easement Cleared 5/18/2023 WALTER RAMIREZ
Hydrant and Access approval Cleared 7/11/2023 MATTHEW CRAIG
Low Impact Development Cleared 7/28/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/28/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/28/2023 LEE GUILBEAUX
Senate Bill 9 Cleared 8/10/2023 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2023 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 9/5/2023 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 9/8/2023 Approved JEFFREY BULL
Underground Mechanical 9/11/2023 Not Ready for Inspection JOHN KIDWELL
Wood Frame 9/11/2023 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 9/13/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Approved JEFFREY BULL
HVAC-Rough 9/26/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 9/26/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 10/19/2023 Approved JEFFREY BULL
HVAC-Rough 10/19/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/19/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 10/19/2023 Approved JEFFREY BULL
Verify Sprinkler Sign Off 10/19/2023 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 10/25/2023 Approved JEFFREY BULL
Green Building Rough 10/25/2023 Approved JEFFREY BULL
Verify Sprinkler Sign Off 10/25/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/30/2023 Approved JEFFREY BULL
Shower Pan 10/30/2023 Approved JEFFREY BULL
Drywall Nailing 11/3/2023 Approved JEFFREY BULL
ELECTRICAL-Final 3/14/2024 Corrections Issued HENRY KIM
Final 3/14/2024 Corrections Issued HENRY KIM
Green Building Final 3/14/2024 Approved HENRY KIM
HVAC-Final 3/14/2024 Corrections Issued HENRY KIM
PLUMBING-Final 3/14/2024 Corrections Issued HENRY KIM
Smoke Detectors 3/14/2024 Approved HENRY KIM
Final 3/27/2024 Not Ready for Inspection ALEXANDER HANDY
Footing/Foundation/Slab 3/27/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 3/27/2024 Not Ready for Inspection ALEXANDER HANDY
Final 5/6/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Not Ready JEFFREY BULL
Service/Power Release 5/6/2024 Not Ready for Inspection JEFFREY BULL
Final 6/24/2024 OK to Issue CofO JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 6/24/2024 Approved JEFFREY BULL