4826 N WOODLEY AVE 91436
Certificate Information: 4826 N WOODLEY AVE 91436
- Application / Permit
- 22010-20000-05427
- Plan Check / Job No.
- B22VN16476
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 63'-11 5/8" X 107'-10 5/8" IRREGULAR SHAPED 2-STORY SFD W/ 3 CAR GARAGE & PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUHGOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | RAPHAEL ROSAS |
| Corrections Issued | 11/15/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/18/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| Applicant returned to address corrections | 1/18/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/24/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 1/30/2023 | RAPHAEL ROSAS |
| Issued | 2/22/2023 | APPLICANT |
| CofO in Progress | 2/23/2024 | VINCENT HANLEY |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
| CofO Issued | 3/6/2024 | JOHN JANSON |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2022 | ROMAN GUTIERREZ |
| Permit | Cleared | 12/15/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 12/23/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 1/6/2023 | LUIS LUVANO |
| Trees in Parkway | Cleared | 1/9/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 1/16/2023 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 1/18/2023 | COLIN LOREDO |
| Certificate of Compliance | Cleared | 1/19/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 4/10/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 6/1/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/2/2023 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 6/2/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/6/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/6/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/6/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/9/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 6/29/2023 | Approved | VINCENT HANLEY |
| Insulation | 7/11/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/11/2023 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 8/21/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 8/21/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| Final | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/14/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| Green Building Rough | 11/14/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| PLUMBING-Final | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| Smoke Detectors | 11/14/2023 | No Access for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/14/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/7/2023 | Corrections Issued | VINCENT HANLEY |
| Final | 12/7/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 12/7/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/7/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 12/7/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/7/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 12/7/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/5/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 1/5/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/31/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/31/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/31/2024 | Approved | VINCENT HANLEY |
| Final | 2/23/2024 | OK to Issue CofO | VINCENT HANLEY |