13828 W CALVERT ST 91401

Certificate Information: 13828 W CALVERT ST 91401

Application / Permit
22010-20000-05415
Plan Check / Job No.
B22VN16441
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E)Garage to ADU and remodeling (E) rec. room, enclose (E) patio to become part of rec.room
Permit Issued
Issued on 3/22/2023
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 SHANGQIN XIE
Corrections Issued 11/11/2022 SHANGQIN XIE
Applicant returned to address corrections 2/24/2023 SHANGQIN XIE
Applicant returned to address corrections 3/16/2023 SHANGQIN XIE
Plan Check Approved 3/19/2023 SHANGQIN XIE
Issued 3/22/2023 APPLICANT
CofO in Progress 7/17/2023 RYAN SALAZAR
Permit Finaled 8/23/2023 RUBEN SALAS
CofO Issued 8/23/2023 RUBEN SALAS
Permit Finaled 8/23/2023 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/15/2023 NADER ISKANDER
Address approval Cleared 3/2/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 3/2/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/6/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Royal Home Builders Inc; Lic. No.: 607619-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/3/2023 Conditional Approval JOHN COLEMAN
Deputy Drilled-In Anchors 4/27/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 5/9/2023 No Access for Inspection RYAN SALAZAR
Green Building Rough 5/9/2023 No Access for Inspection RYAN SALAZAR
PLUMBING-Rough 5/9/2023 No Access for Inspection RYAN SALAZAR
Rough-Elec/Plmb/HVAC 5/9/2023 No Access for Inspection RYAN SALAZAR
Footing/Foundation/Slab 5/10/2023 Approved RYAN SALAZAR
HVAC-Rough 5/10/2023 Approved RYAN SALAZAR
PLUMBING-Rough 5/10/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 5/22/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/22/2023 Partial Approval RYAN SALAZAR
Insulation 5/25/2023 Approved RYAN SALAZAR
Drywall Nailing 5/30/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/26/2023 Approved RYAN SALAZAR
Final 6/26/2023 Corrections Issued RYAN SALAZAR
Green Building Final 6/26/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 6/26/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/26/2023 Approved RYAN SALAZAR
Final 7/7/2023 Partial Approval RYAN SALAZAR
Green Building Final 7/7/2023 Approved RYAN SALAZAR
Final 7/17/2023 OK to Issue CofO RYAN SALAZAR