5308 E OAKLAND ST 1-2 90032

Certificate Information: 5308 E OAKLAND ST 1-2 90032

Application / Permit
22010-20000-05402
Plan Check / Job No.
B22VN07554
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 50'3" X 38' THREE STORY DUPLEX WITH ATTACHED (2) TWO CAR GARAGE AND (2) TWO CAR CARPORTS , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 RARES BODEA
Green Plans Picked Up 6/17/2022 APPLICANT
Corrections Issued 6/21/2022 RARES BODEA
Disabled Access Plans Picked Up 6/21/2022 APPLICANT
Quality Review Completed 6/27/2022 STEVEN KIM
Building Plans Picked Up 6/28/2022 APPLICANT
Applicant returned to address corrections 11/14/2022 RARES BODEA
Applicant returned to address corrections 3/17/2023 RARES BODEA
Plan Check Approved 6/27/2023 RARES BODEA
Issued 7/30/2024 APPLICANT
CofO in Progress 10/2/2025 LILIANA PORTILLO
Permit Finaled 10/4/2025 DEROLD HAUFF
CofO Issued 10/4/2025 DEROLD HAUFF
Permit Finaled 10/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 12/6/2022 ERNEST TSE
Address approval Cleared 12/12/2022 WALLIE JONG
Highway dedication Cleared 12/12/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 12/12/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/15/2022 WALLIE JONG
Sewer availability Cleared 12/15/2022 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 12/22/2022 MIGUEL GAMBOA
Hydrant and Access approval Cleared 2/8/2023 KURT CORRAL
GPI Written Notices Cleared 3/17/2023 RARES BODEA
Grading Pre-Inspection Cleared 3/17/2023 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 9/13/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 9/13/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/25/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/10/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 12/4/2024 Conditional Approval LILIANA PORTILLO
HVAC-Rough 1/14/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 1/14/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 2/4/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/10/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/26/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Approved LILIANA PORTILLO
Shower Pan 2/26/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 2/26/2025 Approved LILIANA PORTILLO
Insulation 3/10/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/10/2025 Approved LILIANA PORTILLO
Drywall Nailing 3/18/2025 Approved JOSH MEISTER
Green Building Rough 3/18/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 3/18/2025 Approved JOSH MEISTER
Underground Mechanical 5/19/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/13/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 8/13/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/3/2025 Approved LILIANA PORTILLO
Gas Test 9/3/2025 Approved LILIANA PORTILLO
PLUMBING-Final 9/3/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/8/2025 Approved LILIANA PORTILLO
Final 9/8/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 9/8/2025 Approved LILIANA PORTILLO
HVAC-Final 9/8/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 9/8/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 9/8/2025 Approved LILIANA PORTILLO
Service/Power Release 9/12/2025 Approved LILIANA PORTILLO
Final 9/29/2025 Conditional Approval LILIANA PORTILLO
Final 10/1/2025 OK to Issue CofO LILIANA PORTILLO