Deputy Reinf. Concrete
|
4/15/2025
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Deputy Reinf. Concrete
|
9/5/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2025
|
Partial Approval
|
MICHAEL ALLEN
|
|
Sewer
|
9/12/2025
|
Approved
|
MICHAEL ALLEN
|
|
Deputy Reinf. Concrete
|
9/18/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
9/18/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
9/18/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
9/23/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/25/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Sewer
|
9/25/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/30/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/3/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/6/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/7/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/7/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/22/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
12/2/2025
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
12/10/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/10/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
12/22/2025
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
12/22/2025
|
Off-Hour Fees Due
|
|
|
Excavation/Setback/Form/Re-Bar
|
12/24/2025
|
No Access for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2025
|
Partial Approval
|
MICHAEL ALLEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2026
|
Partial Approval
|
EVAN COOPER
|
|
Excavation/Setback/Form/Re-Bar
|
2/13/2026
|
Partial Approval
|
EVAN COOPER
|
|
PLUMBING-Rough
|
3/25/2026
|
Partial Approval
|
EVAN COOPER
|
|
Underground Mechanical
|
3/25/2026
|
Partial Approval
|
EVAN COOPER
|
|
Excavation/Setback/Form/Re-Bar
|
4/2/2026
|
Approved
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
4/13/2026
|
Partial Approval
|
EVAN COOPER
|
|
Excavation/Setback/Form/Re-Bar
|
4/13/2026
|
Partial Approval
|
EVAN COOPER
|
|
Deputy Reinf. Concrete
|
4/15/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2026
|
Partial Approval
|
EVAN COOPER
|
|
Excavation/Setback/Form/Re-Bar
|
4/24/2026
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2026
|
Off-Hour Fees Due
|
|
|
Deputy Reinf. Concrete
|
4/28/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
5/5/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
5/5/2026
|
Partial Approval
|
EVAN COOPER
|
|
Deputy Reinf. Concrete
|
5/18/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
5/18/2026
|
Partial Approval
|
EVAN COOPER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/1/2026
|
Partial Approval
|
EVAN COOPER
|
|
Deputy Other (see comments)
|
7/10/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2026
|
Partial Approval
|
RUBEN RIVAS
|
|
Wood Frame
|
7/22/2026
|
Not Ready for Inspection
|
EVAN COOPER
|