10017 N DELCO AVE 91311

Certificate Information: 10017 N DELCO AVE 91311

Application / Permit
22010-20000-05344
Plan Check / Job No.
B22VN16219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
17'-4" X 21'-4" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d).
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2022 APPLICANT
Assigned to Plan Check Engineer 11/15/2022 ALEC MOUSAKHANIAN
Corrections Issued 11/16/2022 ALEC MOUSAKHANIAN
Applicant returned to address corrections 1/14/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 6/26/2023 ROSENDO MEDINA
Applicant returned to address corrections 6/30/2023 ROSENDO MEDINA
Plan Check Approved 7/7/2023 ROSENDO MEDINA
Issued 2/4/2025 APPLICANT
CofO in Progress 11/19/2025 DAVID SCANTLIN
Permit Finaled 11/19/2025 JOHN JANSON
CofO Issued 11/19/2025 JOHN JANSON
Permit Finaled 11/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/5/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/8/2022 COLIN LOREDO
Sewer availability Cleared 12/8/2022 COLIN LOREDO
Construction near power lines Cleared 4/27/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/15/2025 Partial Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 8/18/2025 Corrections Issued KRISTEN CAUSEY
Deputy Drilled-In Anchors 8/19/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 8/19/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 9/17/2025 Approved DAVID SCANTLIN
Shower Pan 9/17/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/24/2025 Approved DAVID SCANTLIN
Green Building Rough 9/24/2025 Approved DAVID SCANTLIN
Insulation 9/24/2025 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 9/24/2025 Approved DAVID SCANTLIN
Drywall Nailing 9/29/2025 Approved DAVID SCANTLIN
Final 11/18/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 11/18/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/18/2025 Approved DAVID SCANTLIN