1373 E 33RD ST 90011

Certificate Information: 1373 E 33RD ST 90011

Application / Permit
22010-20000-05320
Plan Check / Job No.
B22VN16123
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-0" x 23'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 2/11/2023
Issuing Office
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/7/2022 SARKIS HARABEDIAN
Corrections Issued 11/11/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 12/2/2022 SARKIS HARABEDIAN
Plan Check Approved 2/10/2023 JEROME MAGAT PALMA
Issued 2/11/2023 APPLICANT
CofO in Progress 9/26/2023 ALEJANDRO DE ARTOLA
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 11/14/2022 MAX LODER
Redevelopment Project Area Cleared 11/17/2022 DAVID URITA
Address approval Cleared 11/26/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/20/2022 STEVE MELGAR
Sewer availability Cleared 12/20/2022 STEVE MELGAR
Low Impact Development Cleared 1/27/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/8/2023 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/28/2023 Partial Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 4/7/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 4/7/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 4/12/2023 Partial Approval BRENDAN MORELLI
Wood Frame 4/12/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval BRENDAN MORELLI
Insulation 4/13/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 5/23/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 5/23/2023 Approved BRENDAN MORELLI
HVAC-Rough 5/23/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 5/23/2023 Approved BRENDAN MORELLI
HVAC-Rough 5/31/2023 Not Ready for Inspection BRENDAN MORELLI
Wood Frame 5/31/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 6/7/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/7/2023 Approved BRENDAN MORELLI
Green Building Rough 6/15/2023 Approved BRENDAN MORELLI
Insulation 6/15/2023 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 6/15/2023 Approved BRENDAN MORELLI
Drywall Nailing 6/26/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 9/6/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/12/2023 Approved ALEJANDRO DE ARTOLA
Final 9/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/12/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 9/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/12/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/12/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 9/12/2023 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/12/2023 Approved ALEJANDRO DE ARTOLA
Final 9/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/25/2023 Approved ALEJANDRO DE ARTOLA
Final 9/25/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 9/25/2023 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 9/25/2023 Approved ALEJANDRO DE ARTOLA