4336 S VAN BUREN PL 90037

Certificate Information: 4336 S VAN BUREN PL 90037

Application / Permit
22010-20000-05313
Plan Check / Job No.
B22VN16112
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW 43' X 26' ACCESSORY DWELLING UNIT PER GCS65852.2(E)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) ALL WORK PER WFPP.
Permit Issued
Issued on 5/24/2023
Issuing Office
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 LUISANGEL VALENZUELA
Corrections Issued 11/5/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/13/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/28/2023 LUISANGEL VALENZUELA
Plan Check Approved 3/8/2023 LUISANGEL VALENZUELA
Issued 5/24/2023 APPLICANT
CofO in Progress 1/18/2024 SABAS ALONSO
Permit Finaled 2/1/2024 DEROLD HAUFF
CofO Issued 2/1/2024 DEROLD HAUFF
Permit Finaled 2/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/10/2022 JEANIE LAM
Construction near power lines Cleared 1/10/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/18/2023 JEANIE LAM
Sewer availability Cleared 1/18/2023 JEANIE LAM
Low Impact Development Cleared 2/2/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/2/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 6/15/2023 Partial Approval SABAS ALONSO
Sewer 6/15/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 6/22/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/17/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 7/17/2023 Approved STUART CHAPMAN
HVAC-Rough 7/17/2023 Approved STUART CHAPMAN
PLUMBING-Rough 7/17/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 7/17/2023 Approved STUART CHAPMAN
Insulation 7/21/2023 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 7/27/2023 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 7/27/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 12/11/2023 Approved SABAS ALONSO
Drywall Nailing 12/11/2023 Approved SABAS ALONSO
Final 12/11/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 12/11/2023 Corrections Issued SABAS ALONSO
Smoke Detectors 12/11/2023 Corrections Issued SABAS ALONSO
Final 1/5/2024 Corrections Issued SABAS ALONSO
Service/Power Release 1/5/2024 Approved SABAS ALONSO
Smoke Detectors 1/5/2024 Approved SABAS ALONSO
Final 1/8/2024 Corrections Issued SABAS ALONSO
Final 1/17/2024 OK to Issue CofO SABAS ALONSO