4525 N WOODLEY AVE 91436
Certificate Information: 4525 N WOODLEY AVE 91436
- Application / Permit
- 22010-20000-05304
- Plan Check / Job No.
- B22VN16093
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ 2-ATTACHED 4-CAR GARAGES (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Valley
- Current Status
- Issued on 8/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/8/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/14/2022 | APPLICANT |
| Applicant returned to address corrections | 1/31/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/1/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/24/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/31/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/30/2024 | NILOOFAR MEHRAIN |
| Issued | 8/23/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/22/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/22/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/22/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/22/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/22/2022 | CARLOS AGUILERA |
| Permit | Cleared | 12/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/29/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/9/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 1/24/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 2/22/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/28/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Disturb/Remove Protected Trees | Cleared | 6/1/2023 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 8/31/2023 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/31/2023 | NILOOFAR MEHRAIN |
| Excavation more than 5-ft deep | Cleared | 7/30/2024 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/27/2025 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Partial Inspection | JOHN COLEMAN |
| Underground Mechanical | 4/8/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/11/2025 | Conditional Approval | THOMAS FINNILA |
| Sewer | 4/11/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 4/16/2025 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 4/17/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/18/2025 | Conditional Approval | THOMAS FINNILA |
| Sewer | 4/18/2025 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/30/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/1/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 5/2/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 5/6/2025 | Partial Approval | SEAN WIRCH |
| Pre-Inspection | 5/7/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/24/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 6/30/2025 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 7/2/2025 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 7/9/2025 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/9/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 7/11/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 7/11/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/24/2025 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/25/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/25/2025 | Approved | THOMAS FINNILA |
| Insulation | 7/30/2025 | Approved | HENRY KIM |
| Drywall Nailing | 8/12/2025 | Approved | THOMAS FINNILA |
| Underground Mechanical | 10/15/2025 | No Access for Inspection | MORRIS JACKSON |
| Underground Mechanical | 10/30/2025 | Approved | SCOTT SOBEL |