14311 W CALIFA ST 91401

Certificate Information: 14311 W CALIFA ST 91401

Application / Permit
22010-20000-05303
Plan Check / Job No.
B22VN16092
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 30'-9" x 17'-8" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) PER WFPP
Permit Issued
Issued on 5/19/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/2/2022 RAMA DABADGE
Corrections Issued 11/2/2022 RAMA DABADGE
Building Plans Picked Up 11/7/2022 APPLICANT
Applicant returned to address corrections 5/1/2023 ALFRED RAMIREZ
Applicant returned to address corrections 5/2/2023 JESSE ARELLANO
Plan Check Approved 5/5/2023 DANIEL ABRAMYAN
Issued 5/19/2023 APPLICANT
CofO in Progress 11/15/2023 RYAN SALAZAR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/19/2023 COLIN LOREDO
Sewer availability Cleared 1/19/2023 COLIN LOREDO
Construction near power lines Cleared 2/2/2023 RIDWAN HARDY
Low Impact Development Cleared 4/20/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/21/2023 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2023 Partial Inspection RYAN SALAZAR
Underground Mechanical 6/30/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 7/6/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/4/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/4/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 8/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 8/4/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/4/2023 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 8/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
Sewer 8/4/2023 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/4/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/9/2023 Approved RYAN SALAZAR
Gas Test 8/9/2023 Approved RYAN SALAZAR
HVAC-Rough 8/9/2023 Approved RYAN SALAZAR
PLUMBING-Rough 8/9/2023 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/9/2023 Approved RYAN SALAZAR
Sewer 8/9/2023 Approved RYAN SALAZAR
Insulation 8/16/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/16/2023 Partial Approval RYAN SALAZAR
Shower Pan 8/16/2023 Approved RYAN SALAZAR
Drywall Nailing 8/23/2023 Approved RYAN SALAZAR
Green Building Rough 8/23/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/23/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/24/2023 Approved RYAN SALAZAR
Final 10/24/2023 Corrections Issued RYAN SALAZAR
Green Building Final 10/24/2023 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 10/24/2023 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 10/24/2023 Approved RYAN SALAZAR
Final 11/15/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 11/15/2023 Approved RYAN SALAZAR
Service/Power Release 11/15/2023 Approved RYAN SALAZAR