11350 W CHENAULT ST 90049
Certificate Information: 11350 W CHENAULT ST 90049
- Application / Permit
- 22010-20000-05274
- Plan Check / Job No.
- B22VN16019
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (38'-0"x56'-3"), 2081 SQFT 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE (480 SQFT) AND ATTACHED OPEN TRELLIS AT REAR AND FRONT YARDS, W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | PETER MOSESIAN |
| Corrections Issued | 11/6/2022 | PETER MOSESIAN |
| Quality Review Completed | 11/8/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Plan Check Approved | 3/14/2023 | PETER MOSESIAN |
| Issued | 3/16/2023 | APPLICANT |
| CofO in Progress | 3/21/2024 | CARLOS MATAMOROS |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
| CofO Issued | 3/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/10/2022 | LAVEON RIDER |
| Sewer availability | Cleared | 11/15/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2022 | JENSON LEE |
| Specific Plan | Cleared | 2/28/2023 | ROBERT SANCHEZ |
| Low Impact Development | Cleared | 3/14/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/14/2023 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 4/21/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 4/21/2023 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Rough | 4/25/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 4/25/2023 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Subgrade | 4/27/2023 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 4/27/2023 | Approved | CARLOS MATAMOROS |
| Deputy Methane Barrier | 5/5/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 5/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/23/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Barrier | 5/23/2023 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 5/24/2023 | Off-Hour Fees Due | |
| Deputy Reinf. Concrete | 5/25/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 6/1/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/15/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/20/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 6/20/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/20/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | JESUS PINEDA |
| Shower Pan | 6/26/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/30/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/5/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 7/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| MERV13>=Rough | 7/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Rough | 7/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 7/5/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/7/2023 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 7/7/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Rough | 7/7/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 7/11/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 7/17/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/4/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 3/4/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 3/4/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 3/4/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/5/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 3/5/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/5/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/8/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 3/8/2024 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 3/8/2024 | Approved | CARLOS MATAMOROS |
| Final | 3/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/14/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 3/14/2024 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 3/14/2024 | Approved | CARLOS MATAMOROS |
| METHANE-Barrier | 3/14/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 3/14/2024 | Approved | CARLOS MATAMOROS |
| Final | 3/21/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Approved | CARLOS MATAMOROS |