6748 N BEN AVE 91606
Certificate Information: 6748 N BEN AVE 91606
- Application / Permit
- 22010-20000-05266
- Plan Check / Job No.
- B22VN15977
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24'0"X40'6" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING PER SB-9 NEAR FRONT OF LOT. (NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT) <1 OF 4>
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | MARVEL DELACRUZ |
| Corrections Issued | 12/2/2022 | MARVEL DELACRUZ |
| Quality Review Completed | 12/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 12/8/2022 | APPLICANT |
| Plan Check Approved | 5/24/2023 | MARVEL DELACRUZ |
| No Progress | 2/16/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 4/2/2024 | MARVEL DELACRUZ |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 4/28/2026 | GAREN HAYRAPETYAN |
| CofO in Progress | 5/18/2026 | RAUL OLAGI |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2023 | DAGOVERTO GUERRERO |
| Senate Bill 9 | Cleared | 1/26/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/26/2023 | ANACANY HURTADO |
| Hydrant and Access approval | Cleared | 2/17/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/20/2023 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 3/23/2023 | ADALBERTO VERA |
| Permit | Cleared | 5/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/16/2023 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 5/24/2023 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/21/2024 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 10/21/2024 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 11/4/2024 | Approved | JOSE AVILA |
| Pre-Inspection | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 12/6/2024 | Corrections Issued | JOSE AVILA |
| Wood Frame | 3/4/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 4/15/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 4/22/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/22/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 5/6/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | JOSE AVILA |
| Green Building Rough | 6/6/2025 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 6/6/2025 | Approved | JOSE AVILA |
| Insulation | 6/23/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 7/3/2025 | Approved | JOSE AVILA |
| Shower Pan | 8/19/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/24/2025 | Approved | JOSE AVILA |
| Sewer | 9/30/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/30/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 1/30/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 3/2/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/2/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 3/2/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/23/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 4/23/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 4/23/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Final | 4/28/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 4/28/2026 | Approved | GAREN HAYRAPETYAN |