1140 W 25TH ST 90007
Certificate Information: 1140 W 25TH ST 90007
- Application / Permit
- 22010-20000-05253
- Plan Check / Job No.
- B22VN15947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | SELLA BENYAMIN |
| Corrections Issued | 11/4/2022 | SELLA BENYAMIN |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2022 | APPLICANT |
| Plan Check Approved | 5/4/2023 | SELLA BENYAMIN |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | ARTHUR NEGRETE |
| Permit Finaled | 7/31/2024 | DEROLD HAUFF |
| CofO Issued | 7/31/2024 | DEROLD HAUFF |
| Permit Finaled | 7/31/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/1/2022 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 3/20/2023 | RAFAEL FONTES |
| Low Impact Development | Cleared | 4/20/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | WALLIE JONG |
Contact Information
| Contractor | Tf Construction Inc; Lic. No.: 1086111-B | 7720 HAMPTON AVE #104 WEST HOLLYWOOD, CA 90046 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 5/26/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 5/26/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/28/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 6/28/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 6/28/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/19/2023 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 7/19/2023 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 8/17/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/22/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 9/22/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 9/22/2023 | Corrections Issued | STUART CHAPMAN |
| Shower Pan | 9/22/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/28/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 9/28/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 9/28/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 9/28/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 10/6/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 10/11/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 10/16/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 10/20/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Drywall Nailing | 10/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 1/22/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/26/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 1/26/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 1/26/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 1/26/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/12/2024 | No Access for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/14/2024 | Approved | ARTHUR NEGRETE |
| Final | 2/15/2024 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 2/15/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/15/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 2/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 3/29/2024 | OK to Issue CofO | ARTHUR NEGRETE |