15956-15958 W LEMARSH ST 91343

Certificate Information: 15956-15958 W LEMARSH ST 91343

Application / Permit
22010-20000-05242
Plan Check / Job No.
B22VN15903
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New ADU (781sf), 2 car garage, and SB9 (1187sf) unit on 2nd floor
Permit Issued
Issued on 5/17/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 JOE VO
Corrections Issued 11/11/2022 JOE VO
Quality Review Completed 11/14/2022 GARO TELMI
Plan Check Approved 5/15/2023 JOE VO
Issued 5/17/2023 APPLICANT
CofO in Progress 3/7/2024 JAVIER RAMOS JR
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/27/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/27/2022 COLIN LOREDO
Permit Cleared 12/27/2022 COLIN LOREDO
Sewer availability Cleared 12/27/2022 COLIN LOREDO
Hydrant and Access approval Cleared 1/22/2023 KURT CORRAL
Senate Bill 9 Cleared 1/26/2023 NATHAN ROMINE
Low Impact Development Cleared 2/21/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/27/2023 COLIN LOREDO
Construction near power lines Cleared 5/2/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/15/2023 JOE VO

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 6/20/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 7/5/2023 Approved JAVIER RAMOS JR
Deputy Wood Construction 7/27/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Approved JAVIER RAMOS JR
Wood Frame 7/28/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 9/18/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 9/18/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 9/18/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 9/18/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/18/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 9/29/2023 Approved JAVIER RAMOS JR
HVAC-Rough 9/29/2023 Approved JAVIER RAMOS JR
Insulation 9/29/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/29/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 9/29/2023 Approved JAVIER RAMOS JR
Drywall Nailing 10/4/2023 Approved ROBERT GOLD
Green Building Rough 10/4/2023 Approved ROBERT GOLD
Shower Pan 10/19/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/1/2024 Approved JAVIER RAMOS JR
Final 2/1/2024 Corrections Issued JAVIER RAMOS JR
Gas Test 2/1/2024 Approved JAVIER RAMOS JR
Green Building Final 2/1/2024 Approved JAVIER RAMOS JR
Insulation 2/1/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 2/1/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 2/1/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 3/6/2024 Approved JAVIER RAMOS JR
Final 3/6/2024 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 3/6/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 3/6/2024 Approved JAVIER RAMOS JR
Service/Power Release 3/6/2024 Approved JAVIER RAMOS JR
Smoke Detectors 3/6/2024 Approved JAVIER RAMOS JR