15956-15958 W LEMARSH ST 91343
Certificate Information: 15956-15958 W LEMARSH ST 91343
- Application / Permit
- 22010-20000-05242
- Plan Check / Job No.
- B22VN15903
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New ADU (781sf), 2 car garage, and SB9 (1187sf) unit on 2nd floor
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | JOE VO |
| Corrections Issued | 11/11/2022 | JOE VO |
| Quality Review Completed | 11/14/2022 | GARO TELMI |
| Plan Check Approved | 5/15/2023 | JOE VO |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 3/7/2024 | JAVIER RAMOS JR |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | COLIN LOREDO |
| Permit | Cleared | 12/27/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/27/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 1/22/2023 | KURT CORRAL |
| Senate Bill 9 | Cleared | 1/26/2023 | NATHAN ROMINE |
| Low Impact Development | Cleared | 2/21/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/27/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 5/2/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/15/2023 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/12/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/20/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/5/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/27/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 7/28/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/18/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 9/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/18/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/29/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 9/29/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/4/2023 | Approved | ROBERT GOLD |
| Green Building Rough | 10/4/2023 | Approved | ROBERT GOLD |
| Shower Pan | 10/19/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| Gas Test | 2/1/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 2/1/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 2/1/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/1/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 2/1/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/6/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/6/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 3/6/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/6/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/6/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/6/2024 | Approved | JAVIER RAMOS JR |