6606 N LANKERSHIM BLVD 91606

Certificate Information: 6606 N LANKERSHIM BLVD 91606

Application / Permit
22010-20000-05224
Plan Check / Job No.
B22VN15475
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Carport
Work Description
ePLAN. (N) CARPORT #1
Permit Issued
Issued on 2/3/2023
Issuing Office
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 LAMAR DAVIS
Corrections Issued 10/25/2022 LAMAR DAVIS
Quality Review Completed 10/26/2022 GARO TELMI
Applicant returned to address corrections 12/29/2022 DANIEL YIP
Plan Check Approved 2/3/2023 DANIEL YIP
Issued 2/3/2023 APPLICANT
CofO in Progress 10/24/2023 JOHN KITCKO
Permit Finaled 11/17/2023 RICKEY JACKSON
CofO Issued 11/17/2023 RICKEY JACKSON
Permit Finaled 11/17/2023 RICKEY JACKSON

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 11/30/2022 NELSON RODRIGUEZ
Comm Cor/Mini-Mall Cleared 11/30/2022 NELSON RODRIGUEZ
Comm Cor/Mini-Mall Cleared 11/30/2022 NELSON RODRIGUEZ
Green Code Cleared 11/30/2022 MICHAEL AYERS
Hydrant and Access approval Cleared 12/4/2022 JOHN CONNEALLY
Low Impact Development Cleared 12/5/2022 ANDRES COVARRUBIAS
Address approval Cleared 12/6/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/6/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/7/2022 CARLOS AGUILERA
DAS Clearance Cleared 12/8/2022 NORLITO MEDRANO
Highway dedication Cleared 1/31/2023 CARLOS AGUILERA

Contact Information

Contractor Sipan Design & Development Inc; Lic. No.: 885235-B       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/14/2023 Not Ready for Inspection JOHN KITCKO
Piling/Pier/Caisson 4/18/2023 Partial Approval JOHN KITCKO
Structural Steel Frame 7/13/2023 Approved JOHN KITCKO
Final 8/24/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 8/24/2023 Approved JOHN KITCKO
Green Building Final 8/24/2023 Approved JOHN KITCKO
Green Building Rough 8/24/2023 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved JOHN KITCKO
Smoke Detectors 8/24/2023 Approved JOHN KITCKO
Wood Frame 8/24/2023 Approved JOHN KITCKO
Final 10/24/2023 OK to Issue CofO JOHN KITCKO