5057 N BLUEBELL AVE 91607
Certificate Information: 5057 N BLUEBELL AVE 91607
- Application / Permit
- 22010-20000-05187
- Plan Check / Job No.
- B22VN15254
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-Story Single Family Dwelling with attached 2-Car Garage VB R-3 Occupancy (Fully Sprinklered per NFPA-13D)
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JAD BASMA |
| Corrections Issued | 10/23/2022 | JAD BASMA |
| Quality Review Completed | 10/27/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/23/2022 | JAD BASMA |
| Plan Check Approved | 12/6/2022 | JAD BASMA |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 1/17/2024 | JOSE AVILA |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| CofO Issued | 3/20/2024 | RUBEN SALAS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/1/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 11/4/2022 | CHRISTIAN PEARSON |
| Low Impact Development | Cleared | 11/8/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/8/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 11/19/2022 | RUEL COLE |
| Address approval | Cleared | 11/30/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/14/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 4/5/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Partial Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 6/2/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 6/8/2023 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 6/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 6/9/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/20/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 6/20/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 6/20/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 6/28/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/28/2023 | Approved | KIRK SANDERS |
| Shower Pan | 6/28/2023 | Corrections Issued | KIRK SANDERS |
| Verify Sprinkler Sign Off | 6/28/2023 | Approved | KIRK SANDERS |
| Insulation | 7/6/2023 | Approved | JUAN VALENZUELA |
| Shower Pan | 7/6/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 7/18/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/18/2023 | Approved | KIRK SANDERS |
| Final | 1/9/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 1/9/2024 | Approved | JOSE AVILA |
| Final | 1/12/2024 | OK to Issue CofO | JOSE AVILA |
| Gas Test | 1/12/2024 | Approved | JOSE AVILA |
| Green Building Final | 1/12/2024 | Approved | JOSE AVILA |
| HVAC-Final | 1/12/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 1/12/2024 | Approved | JOSE AVILA |
| Service/Power Release | 1/12/2024 | Approved | JOSE AVILA |