19502 W LANARK ST 91335
Certificate Information: 19502 W LANARK ST 91335
- Application / Permit
- 22010-20000-05178
- Plan Check / Job No.
- B22VN15711
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 44'-4" X 66'-11" SINGLE FAMILY DWELLING W/ 5' X 19'-9" & 5' X 22' TRELLIS PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | RAPHAEL ROSAS |
| Corrections Issued | 11/15/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 11/18/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| Plan Check Approved | 12/20/2022 | RAPHAEL ROSAS |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 11/21/2023 | JEFFREY BULL |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
| CofO Issued | 11/21/2023 | JOHN JANSON |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/7/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | CARLOS AGUILERA |
| Address approval | Cleared | 12/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/13/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/14/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/13/2023 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 3/13/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 4/3/2023 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 4/10/2023 | Approved | SEAN HAUPT |
| Wood Frame | 4/28/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/10/2023 | Conditional Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 5/10/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 5/10/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 5/10/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/10/2023 | Approved | JEFFREY BULL |
| Sewer | 5/10/2023 | Approved | JEFFREY BULL |
| Insulation | 5/16/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 5/16/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/22/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/22/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 10/19/2023 | Approved | JEFFREY BULL |
| Final | 10/19/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 10/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 10/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 10/19/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 10/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 10/19/2023 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 10/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | JEFFREY BULL |
| Final | 11/21/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 11/21/2023 | Approved | JEFFREY BULL |
| Service/Power Release | 11/21/2023 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 11/21/2023 | Approved | JEFFREY BULL |