5928 N CORBIN AVE 91356
Certificate Information: 5928 N CORBIN AVE 91356
- Application / Permit
- 22010-20000-05173
- Plan Check / Job No.
- B22VN15691
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 5/3/2023
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | DANIEL YIP |
| Corrections Issued | 11/21/2022 | DANIEL YIP |
| Plan Check Approved | 4/27/2023 | DANIEL YIP |
| Issued | 5/3/2023 | APPLICANT |
| CofO in Progress | 11/1/2024 | JON MCHUGH |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
| CofO Issued | 11/12/2024 | JOHN JANSON |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 2/3/2023 | FERNANDO GIL |
| Low Impact Development | Cleared | 4/6/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/24/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | J M A General Contractor ; Lic. No.: 893018-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/12/2023 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 5/12/2023 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 5/22/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 6/16/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 6/16/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/3/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 7/3/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/3/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 8/14/2023 | Approved | JON MCHUGH |
| Green Building Rough | 8/14/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 8/14/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 8/14/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 8/14/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/23/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 8/23/2023 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/23/2023 | Partial Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/7/2023 | Partial Inspection | MORRIS JACKSON |
| Sewer | 1/25/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Sewer | 2/22/2024 | Corrections Issued | JON MCHUGH |
| Sewer | 2/29/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 4/5/2024 | Partial Approval | JON MCHUGH |
| Gas Test | 4/18/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/30/2024 | Corrections Issued | JON MCHUGH |
| Final | 8/30/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 8/30/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 8/30/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 10/2/2024 | Approved | JON MCHUGH |
| Final | 10/2/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/2/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/2/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 10/2/2024 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 10/2/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 10/23/2024 | Approved | JON MCHUGH |
| Final | 10/23/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 10/23/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 10/23/2024 | Approved | JON MCHUGH |
| Final | 10/31/2024 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 10/31/2024 | Approved | JON MCHUGH |
| Final | 11/1/2024 | OK to Issue CofO | JON MCHUGH |