19643 W GREENBRIAR DR 91356

Certificate Information: 19643 W GREENBRIAR DR 91356

Application / Permit
22010-20000-05169
Plan Check / Job No.
B22VN15198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 800 SQFT ADU PER STATE LAW
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 3/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 JAD BASMA
Corrections Issued 10/22/2022 JAD BASMA
Quality Review Completed 10/31/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/24/2023 JAD BASMA
Plan Check Approved 5/2/2023 JAD BASMA
Issued 5/8/2023 APPLICANT
CofO in Progress 3/4/2026 JOHN KIDWELL
Permit Finaled 3/7/2026 MICHAEL PELHAM
CofO Issued 3/7/2026 MICHAEL PELHAM
Permit Finaled 3/7/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 11/8/2022 CARLOS AGUILERA
Street Frontage Cleared 11/8/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/9/2022 CARLOS AGUILERA
Sewer availability Cleared 11/9/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/6/2022 RUEL COLE
Low Impact Development Cleared 3/7/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 3/9/2023 DAGOVERTO GUERRERO
GPI Written Notices Cleared 5/2/2023 JAD BASMA
Grading Pre-Inspection Cleared 5/2/2023 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/9/2023 Partial Approval SEAN HAUPT
PLUMBING-Rough 8/9/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 8/18/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 1/3/2024 Not Ready for Inspection JEFFREY PARD
Green Building Rough 1/3/2024 Not Ready for Inspection JEFFREY PARD
Shower Pan 1/3/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 1/3/2024 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/21/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 2/21/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 5/3/2024 Approved JOHN KIDWELL
HVAC-Rough 5/3/2024 Approved JOHN KIDWELL
PLUMBING-Rough 5/3/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/12/2024 Approved JOHN KIDWELL
Green Building Rough 7/12/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 7/12/2024 Approved JOHN KIDWELL
Drywall Nailing 9/13/2024 Approved JOHN KIDWELL
Insulation 9/13/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/19/2024 Partial Approval JOHN KIDWELL
Shower Pan 11/19/2024 Partial Inspection JOHN KIDWELL
Gas Test 2/28/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Ready JOHN KIDWELL
Gas Test 4/7/2025 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 4/7/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 9/24/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 9/29/2025 Approved JOHN KIDWELL
HVAC-Final 9/29/2025 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 9/29/2025 Approved JOHN KIDWELL
HVAC-Final 1/5/2026 Approved JOHN KIDWELL
Final 2/18/2026 Not Ready for Inspection JOHN KIDWELL
Green Building Final 2/18/2026 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved JOHN KIDWELL
Smoke Detectors 2/18/2026 Approved JOHN KIDWELL
Final 3/3/2026 OK to Issue CofO JOHN KIDWELL