151 S WESTGATE AVE 90049
Certificate Information: 151 S WESTGATE AVE 90049
- Application / Permit
- 22010-20000-05166
- Plan Check / Job No.
- B22VN15680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW (12'-0"x20'-0"), 164 SQFT PATIO COVER W/ATTACHED EXTERIOR ACCESSED BATHROOM
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | PETER MOSESIAN |
| Corrections Issued | 11/2/2022 | PETER MOSESIAN |
| Quality Review Completed | 11/8/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 11/9/2022 | APPLICANT |
| Plan Check Approved | 2/2/2023 | PETER MOSESIAN |
| Issued | 2/17/2023 | APPLICANT |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/7/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/10/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/2/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 8/3/2023 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/14/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/31/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/2/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/9/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/13/2023 | Corrections Issued | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 11/13/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/22/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 11/27/2023 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 11/27/2023 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/14/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 1/16/2024 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 1/18/2024 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/22/2024 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 1/29/2024 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 6/5/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Final | 10/10/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/10/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/15/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/15/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/15/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/15/2024 | Approved | JESUS RODRIGUEZ |